27-MAY-2020 |
|
14 standalone flexible hose replacement
1 well riser needed and replaced so as to clear ground level
X457, Z341 Z343, Z346, E492, E493, F495, F496, F497, F498, G499, G500 , G501, G502 |
|
26-MAY-2020 |
|
Pick up ute and equipment from run factory
Go to MRL
X160 and x161 and x162 repairs done completed |
|
25-MAY-2020 |
|
0645 Pick up 4x4 from factory with some fittings
0730 go to container in regional site 20 load up genset, qbox and tooling ,parts etc
Drive to MRL
Commenced working at 1030 mrl
1430 head back to run factory need more parts to repair struts on standalones etc
Unload equipment at regional site 20 container
Wash ute
|
|
04-MAY-2020 |
William (Daniel) Williams |
Replace flexi pipe on wells
Prepare tools container for pickup
|
|
01-MAY-2020 |
William (Daniel) Williams |
Expose leachate lines .elbow and cap of line
Flexi hose extensions |
|
30-APR-2020 |
William (Daniel) Williams |
Lay ,tie in weld 90mm leachate jump line from LP22
Replace and extend flexi hose on stand alone wells h504,h505,d489,d490 d491 ,run energy wells |
|
29-APR-2020 |
William (Daniel) Williams |
Travel from Clayton to MRL
Catch up with Tommy and discuss what works need to be performed |
|
27-APR-2020 |
William (Daniel) Williams |
Locate leachate line
Cut and tee in to existing |
|
23-APR-2020 |
William (Daniel) Williams |
Level pad to lay new leachate line from LP21 toLP22
Uncoil 63mm poly pipe
Expose old line and tie in points,cut and ca
Lay new line tie in,weld,90m approx
Trip to Clayton to drop off furphy and pick up parts for mrl |
|
22-APR-2020 |
William (Daniel) Williams |
Sand up trench and Back fill tidy up at stage 4 road crossing
Cart sand and poly pipe to stage 2
Trench from lp18 to q175 and lay approx 70m
Lay tie in and weld a new 63mm leachate line
Sand up,Back fill,tidyup
|
|
21-APR-2020 |
William (Daniel) Williams |
Trench top side of haul road
Lay leachate line and tie in
Cart sand from stockpile to trench
Cap off 160mm riser |
|
20-APR-2020 |
William (Daniel) Williams |
Uncoil 63mm and110mm poly pipe
Bench in a couple of pads on bottom side of haul road
Make trench to lay pipe along batter
Feed poly pipe through sleeves
Variation work |
|
19-APR-2020 |
William (Daniel) Williams |
Excavate trench across main haul road
Lay two sleeves across for air and leachate lines
Backfill and compact tidy up
Variation works |
|
17-APR-2020 |
William (Daniel) Williams |
No one on site
Excavator stood down from today - no charge as notified to Rhodes by Reg on the 15th April |
|
16-APR-2020 |
William (Daniel) Williams |
Works under Variation #2 & #3
Straighten poles n struts
Fix leachate line at sump
Cleaned up equipment and put on stand down
Drive back to office to swap vehicles zbg667 crane ute ops for UVX685 that had been repaired at JV Motors
Back to MRL to park Dump Truck where it could be picked up by OneTrak
|
|
16-APR-2020 |
William (Daniel) Williams |
Repair struts and poles and tidy up around sump
Make a track for Ute to get to sump
Repair leaking leachate line clean area
Variation work
*****DUPLICATED |
|
15-APR-2020 |
William (Daniel) Williams |
Works under Variation #1 & #2
Repair leachate line and replace valve and weld
Hard cap 2x 160mm coup and hard caps at location as per Tom Mathews instruction
Relocate digger to cell 3b clear work area and back fill hole around kop and air n leachate pipes
|
|
14-APR-2020 |
William (Daniel) Williams |
Lay and weld flowlines through haul road crossing
Backfill tidy up site area take down flagging and star pickets
Take rubbish to tip face
Relocate sand and rock down to stockpile |
|
12-APR-2020 |
Richard Andrews |
Road crossing - trench and install 160mm sleeves, back fill and clean up. |
|
09-APR-2020 |
Richard Andrews |
Clean up mud from proposed trench line and replace with dry fill.
Trench weld and lay 40m of 90mm flow line.
Weld and lay 80m of 90mm flow lines.
Back fill aand clean up.
Connect flow lines to manifold.
Back fill around manifold pad and spread with rock.
Get sleeves ready for road crossing Sunday. |
|
08-APR-2020 |
Richard Andrews |
Dig and install 1 J trap.
Back fill and clean up.
Relocate stockpiles of sand to edge of road.
Receive 1 tandem load of sand.
Pull down flagging and star pickets.
Clean up stockpiles of rubbish.
Clean up work area as best we can in conditions.
Clean and swap vehicles.
Rain on and off in morning, site extremely wet. |
|
07-APR-2020 |
Richard Andrews |
Load up coils and take to work area.
Clean up mud from proposed trench line.
Trench weld and lay 70m of 90mm flow line.
Back fill and clean up.
Cart some loads of rubbish to tip face.
Site still extremely wet. |
|
06-APR-2020 |
Richard Andrews |
Rained off, site extremely wet from weekends rain.
Sort out fittings and clean up containers.
Take a load of fittings to office.
Pick up J traps from from Clayton and drop off back at MRL. |
|
03-APR-2020 |
Richard Andrews |
Build pad for well station manifold.
Put together manifold and erect on pad.
Weld and lay 20m of 160mm header line from well station to netting.
Pull down flagging where horizontals were installed and flag off open holes.
General clean up of work area.
Wash vehicles.
Site extremely wet, unable to do road crossing in these conditions. |
|
02-APR-2020 |
Richard Andrews |
Trench weld and lay 100m of 90mm horizontal well.
Install 2 x droppers.
Back fill and clean up.
Finish putting together well station manifold.
Flag off open holes.
Sort out fittings for job completion.
Cart some excess rubbish to tip face.
|
|
01-APR-2020 |
Richard Andrews |
Trench weld and lay 100m of 90mm horizontal well.
Install 2 x droppers.
Back fill and clean up.
Cart excess rubbish to tip face.
Dump truck delivered to site.
Receive 1 truck and dog of rock and 1 truck and dog of dust. |
|
31-MAR-2020 |
Richard Andrews |
Trench weld and lay 100m of 90mm horizontal well.
Install 2 x condensate droppers.
Back fill and clean up.
Stockpile excess rubbish and cover.
2 x truck and dog of 50mm ballast received. |
|
30-MAR-2020 |
Richard Andrews |
Site induction for RA.
Meet with site supervisor, run through plan to complete works.
Drag 90mm pipe for horizontals up to work area.
Bring coil and 160mm pipe up to work area.
Flag off work area.
Clean up area's for stock piles and manifold.
Pick up manifold and fuel pod fro office. |
|
28-FEB-2020 |
William (Daniel) Williams |
Inductions, meetings with cleanaway and permits. |
|
27-FEB-2020 |
William (Daniel) Williams |
Make up drain pipe for horizontals
Check out pipe on site if it can be useable
Check out what tools are available
clean up sheds |