11973
MRL Repair 8 Flowlines
Cleanaway Waste Management Ltd
Melbourne Regional Landfill
1100-1152 Christies Rd, Ravenhall, Victoria 3023 Australia

Complete
Landfill Gas Collection System Remediation 

Run Energy will:

  • Trench, weld and lay flow line
  • Weld and lay flow line
  • Install J-traps
  • Install in accordance with attached design drawing:
    • MRL - Gas Collection System - Flow Line Replacement - MRL-GCS-003

Details:

Item Quantity/Size Installation Notes General Arrangement Drawing Reference
Flow line 266 m x 90 mm  PN10

Trench, weld and lay flow line to a minimum 2% fall  inclined to wells:

  • U232
  • S223
  • S385
  • R202
RE-LFG-002
Flow line  310 m x 90 mm  PN10

Weld and lay flow line to the gradient of the landfill cap to connect wells;

  • L150
  • Z320
  • P269
  • P286
RE-LFG-002
J-trap 2 x 90 mm PN10
  • Drill and install in low points on flow lines to wells S223 & R202
  • Locations to be confirmed on site
RE-LFG-006
  • No variations
Landfill Gas Collection System Remediation 

Run Energy will:

  • Trench, weld and lay flow line
  • Install J-traps
  • Install in accordance with attached design drawing:
    • MRL - Gas Collection System - Flow Line Replacement - MRL-GCS-003

Details:

Item Quantity/Size Installation Notes General Arrangement Drawing Reference
Flow line

576 m x 90 mm PN10

Trench, weld and lay flow lines to a minimum 2% gradient  to wells:

  • U232
  • S223
  • S385
  • R202
  • L150
  • Z320
  • P269
  • P286
RE-LFG-002
J-trap 2 x 90 mm PN10
  • Drill and install in low points on flow lines to wells S223 & R202
  • Locations to be confirmed on site
RE-LFG-006
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1 Practical Completion Day 5 Yes   Yes  
2    
3    
4    
5    
6    
7    
8    
9    
10    
 
Date Issued
Equipment Type
Equipment Serial ID
 
11973  (5 Record records) 
27-MAR-2020   565075
04-MAR-2020 Personal Gas Monitor KA416-1056664
28-FEB-2020 Personal Gas Monitor KA416-1073321
27-FEB-2020 Personal Gas Monitor KA416-1073321
27-FEB-2020 Personal Gas Monitor KA416-1056664
 
Date
Team Lead
Work Summary
 
11973 - MRL Repair 8 Flowlines  (7 Daily Log records) 
27-MAR-2020 William (Daniel) Williams Install flow line from u station to well #227
05-MAR-2020 William (Daniel) Williams Works shut down due to weather only one flowline left U227 as per discussion with Reg will be put off till we return to install horizontals
04-MAR-2020 William (Daniel) Williams Excavate and install jtraps to S385 & S223. Trench weld and lay flowline to S223 approx 70m. Make connections at well and manifolds on both wells backfill and reinstate area.
03-MAR-2020 William (Daniel) Williams Excavate and install jtrap to R202 the trench weld and lay flowline from trap to manifold approx 30m. Make connection at manifold and back area. Trench through road crossing at S station down to trap location. Trench weld and lay flowline approx 100m and back fill
02-MAR-2020 William (Daniel) Williams Weld and lay approx 170m of above ground flowlines to wells L150, Z320 & Z321. Expose manifolds cap off old flowlines and make new connections at both ends. Start trenching R202 from well to low point ready for jtrap approx 30m backfill and reinstate area.
28-FEB-2020 William (Daniel) Williams Late start due decisions made by cleanaway to put off for two weeks. Loaded up 6 coils in Moxy and transported up to work location in two loads. Use excavator to make paths to P286 & P269. 269 needed to cut through the hill to make it work may need to trench through hill after checking fall with level this morning.
Weld and lay 180m of flowine made connections at manifold and well ends. Tommy been told they ready for commissioning.

Water furphy to run equipment
27-FEB-2020 William (Daniel) Williams Pull out Valve, refurbish valve and re-install valve
Variation 1
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
13-MAY-2020 Melbourne Regional Landfill Job GCS As-Built Flow line replacement as built 11973 11973 Dwg
No
No
No
No
Reg Blair
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.