06-AUG-2021 |
Richard Andrews |
Weld and lay 30m of 90mm flow line to connect S385 to well station
Expose and repair S223
Back fill and clean up
Clean up pipe
Clean and off hire machine |
|
05-AUG-2021 |
Richard Andrews |
Drive to Clayton and pick up trailer and coil, drive to MRL.
Receive excavator and track up to work area.
Pull out coil.
Expose flow line at both ends, cut and remove.
Weld and lay 70m of 90mm flow line and connect.
Investigate other damaged flow lines.
Variation - repair air and leachate lines hit by dozer.
|
|
04-AUG-2021 |
Richard Andrews |
Pick up trailer from MRL and load up coil and Clayton.
Organise and load up fittings. |
|
26-JUL-2021 |
Andrew Keys |
Var. #17:
1) Drove from Clayton to MRL
2) met with Dave Brown on Site
3) Prepped and repaired approximately 2.5m of 90mm Leachate Line.
4) Drove back Clayton Regional |
|
09-JUL-2021 |
|
Var 12 & Var 15 continued:
- Exposed Barra Trap
- Cut off 6" and allowed Header line fall to Barra Trap
- Tee in 63/110 Leachate line
- Backfilled exposed Header line
- Returned Excavator to Kennards |
|
08-JUL-2021 |
|
- picked up Excavator from Kennards
- Exposed H Header line & excavate Trap
- Assist Landtrak exposing 2 x damaged flow lines for 2 hours |
|
01-JUL-2021 |
|
Re-connected the following flow lines;
- M540
- M537(373)
- M538
- LP25R |
|
28-JUN-2021 |
Richard Andrews |
RWCU3036499 L/room 28June - 30June |
|
21-JUN-2021 |
Richard Andrews |
RWCU3036499 L/room 21June - 27June |
|
14-JUN-2021 |
Richard Andrews |
RWCU3036499 L/room 14June - 20June |
|
07-JUN-2021 |
Richard Andrews |
RWCU3036499 L/room 31 May - 06June |
|
01-JUN-2021 |
Richard Andrews |
RWCU3036499 L/room 31 May - 06June |
|
31-MAY-2021 |
Dayne Bramich |
Raised Leachate Sump LP02 x 3m (final height). |
|
24-MAY-2021 |
Richard Andrews |
RWCU3036499 L/room 24 - 30 May
|
|
19-MAY-2021 |
Richard Andrews |
OR087 excavator 19 May Machine used Ops J#12156
Only used for today & then off hired |
|
17-MAY-2021 |
Richard Andrews |
RWCU3036499 L/room 17 - 23 May
Charge Wed 19 May Ops J#12156 |
|
10-MAY-2021 |
Richard Andrews |
OR029 excavator 10th May - 16th May Stood down no charge from supplier
RWCU3036499 L/room 10th May - 16th May
Note: Lunch room is to remain on site until the next project.
Excavator was off hired today and returned to Onetrak |
|
04-MAY-2021 |
Richard Andrews |
OR029 excavator 4 May Machine used Ops J#12156
RWCU3036499 L/room 3 - 9 May
charge Tues day 4 May Ops J#12156 |
|
03-MAY-2021 |
Richard Andrews |
OR029 excavator 3 May Stood down no charge from supplier
OR029 excavator 4 May Machine used Ops J#12156
OR029 excavator 5 - 9 May Stood down no charge from supplier
RWCU3036499 L/room 3 - 9 May
charge Tues day 4 May Ops J#12156 |
|
30-APR-2021 |
Richard Andrews |
OR029 excavator 26th - 2nd May Stood down no charge from supplier
RWCU3036499 L/room 26th - 2nd May |
|
28-APR-2021 |
Richard Andrews |
Trench and install 12m of 225mm sleeve across tank rd.
Join together short lengths of 110mm.
Pull out 110mm coil.
Weld and lay 215m of 110mm leachate line.
Weld and lay 15m of 90mm leachate line.
Put together and install 100mm valve.
2 x tie ins.
|
|
21-APR-2021 |
Richard Andrews |
OR024 excavator 21st- 25th April Stood down no charge from supplier
RWCU3036499 L/room 21st-23rd
|
|
20-APR-2021 |
Richard Andrews |
Divert leachate line to try and release pressure.
Install pressure gauges and monitor pumps.
Cover 110mm sleeve to LP2.
Track machine back to laydown yard.
Trouble shoot pump and leachate line.
Equipment has been stood down - refer phone call Phil & Rhodes. |
|
19-APR-2021 |
Richard Andrews |
Re-lay flow lines and connect wells 2M530, 2M536 and 2M531.
Back fill around tie in points and pin flow lines.
Build up pad around LP2 and hook wire and cable up out of the way.
Look at leachate line solution. |
|
15-APR-2021 |
Richard Andrews |
OR024 excavator stooddown 15th - 18th April
RWCU3036499 L/room 15th and 16th April |
|
14-APR-2021 |
Richard Andrews |
Track machine over to boral.
Pull out 3 x 110mm coils and pin straight.
Make access track near LP38 so we can pull coils into place.
Weld and lay 300m of 110mm leachate line.
Clamp off and tie in.
Check and monitor pumps.
Pin pipe with dirt.
Track machine back to pick up area.
Note: Excavator ID OR24, Bucket ID OT12 & OT87 |
|
13-APR-2021 |
Richard Andrews |
Install air relief valve at LP40.
Start packing up lunch room.
Pump out LP39.
Go to office and collect fittings.
Receive 110mm coils. |
|
12-APR-2021 |
Richard Andrews |
Pump out LP39. |
|
10-APR-2021 |
Richard Andrews |
Install 4 x pressure relief valves.
Investigate leachate line and check pumps. |
|
09-APR-2021 |
Richard Andrews |
Cut and remove flow lines for landtrack. |
|
05-APR-2021 |
Richard Andrews |
RWCU3036499 L/room 5th - 8th April |
|
30-MAR-2021 |
Richard Andrews |
Excavator on site 14T |
|
29-MAR-2021 |
Richard Andrews |
Excavator on Site - 14T |
|
26-MAR-2021 |
Richard Andrews |
Isolate air line and bleed.
Expose air line and repair.
Expose flow line.
Install metre run.
Weld and lay 90mm flow line.
Tie in.
Back fill and clean up. |
|
20-MAR-2021 |
Richard Andrews |
Weld and lay 550m of 110mm leachate line.
Tie in leachate line.
Install 2 x sleeves.
Pin leachate line.
Check for leaks.
|
|
19-MAR-2021 |
Richard Andrews |
Go to office and collect fittings.
Level off ground for pipe to lay on.
Put together valves.
Clamp off leachate line.
Cut in tee and install valves.
Receive 5 coils of 110mm and unload.
Pull out coils and stretch straight. |