27-AUG-2021 |
Andrew Keys |
1) arrived at site location to find no Cree staff on site to carry out the required excavations
2) went up to Landfill and spoke with (Mal) who suggested he could have a digger down there on monday morning.
3) Called Russ to advise of the situation, agreed to come back to Clayton and do a raise at Carroll road for Reg.
4) Russ called back just as we got top the city and said there was a Cree employee heading to MRL to do the excavation works
5) Returned to site
6) Removed the mound from around the bore, excavated down 500mm
7) Installed 6 bags of Bentonite and wet down
8) Reinstated around the bore with clay
9) Concreted in the yellow Lid
10 Made a physical bund around the bore to ensure it doesn't get damaged by trucks etc
Kate arrived as we finished and seemed quit happy |
|
26-AUG-2021 |
Andrew Keys |
1) Disconnected the air and Leachate discharge line on the Leachate sump
2) Removed pump from the sump (please note the pump was hanging at 14m)
3) Extended the leachate line, control cable, air line etc to allow us to raise the sump casing
4) Raised the 225mm sump 3m
5) Raised the conduit housing the air and leachate lines 3m
6) Carted in fill and made mound around the sump to hold it straight and to gain access to re install the pump
7) Installed pump at 17m and fitted off |
|
25-AUG-2021 |
Andrew Keys |
1) Pops and myself arrived at site at approx. 12.00pm
2) after lunch we located the damaged 90mm flow line U487
3) prepped each side of the damaged flow line
4) Cut out the damaged section and replaced with approx. 5m of good 90mm
5) welded 2 x 90mm couplers
6) Allowed welds to cool and turned the isolation valve back on
Please note: these works were carried out in-between rain showers |
|
19-AUG-2021 |
Andrew Keys |
1) Arrived at site and signed on
2) Keysy caught up on the last 2 days logs and time sheets
3) Pops and Keysy relocated all the long strings of pipe from site 1 over to the lay down yard adjacent to the Gas plant at MRL
4) Hooked up the furphy and took to Victory road for Dog
5) Loaded up J.B's Tool box and dropped off at Victory road for him
6) Cut all scrap pipe down into 1M lengths and placed in the skip bin near Gas plant |
|
18-AUG-2021 |
Andrew Keys |
SITE 1 - V02 Clean up works
1) Arrived at site at aprox 11.00am
2) Met with Dave Brown whom escorted us over to Site 1
3) Spoke to Rob and Russ RE the scope just to clarify
4) Gut down all small pipe ready to go in the bin
5) Cut up all the Galv frame water sprinkler system ready to go in the bin
6) Loaded up the old tin garden shed and put in the bin
7) Hooked up all the 200mm pipe work and relocated to the Eastern boundary fence adjacent to the Boral Masonry yard
8) Picked up the little digger from Kennards at 1.00pm, unloaded digger at site, excavated around the Galv tank so we could remove it and relocate it.
9) loaded up the little digger and took back to kennards, off hired at aprox 3.30pm
Please note - scope has now changed and we are required to relocate all the pipe work down to the Lay down yard at the GAs plant |
|
08-AUG-2021 |
Andrew Keys |
Works complete
|
|
07-AUG-2021 |
Andrew Keys |
1) Load up all gear required for todays work
2) Install pipe bedding
3) Install 90mm flow lines and back fill
4 Install 5 x Standalone Well set ups on top of the batter
5) Install 5 x traps
6) Backfill and tidy up
7) GPS all pipe work
|
|
06-AUG-2021 |
Andrew Keys |
1) Pulled out the last x coils required for the 90mm flow lines to each stand alone set up.
2) Measured and cut each flow line to desired length
3) Trenched 4 x flow lines aprox 15m length each
4) Excavated low points for the trap installation
Please note pipe bedding material arrived on site at 3.00pm
Please note - Dayne assisted with works from lunch time onwards as he and Dog had finished there scope of works
Please note the small moxy is on standby |
|
06-AUG-2021 |
Andrew Keys |
Duplicate
|
|
05-AUG-2021 |
Andrew Keys |
1) Loaded coils on trailer, pulled out and perforated 120m
2) Trenched 120m
3) Laid 120m of 90mm Horizontal
4) Installed 50/60mm Ballast
5) Backfilled and compacted
As per A Keys....SPH238 only used for 1/2 day til lunch time and then off hired |
|
04-AUG-2021 |
Andrew Keys |
1) Marked out the days trench
2) Pulled out 2 x 90mm coils
3) Perforated 2 x 90mm coils
4) Trenched 180m - Bloody good going
5) Installed 180m of 90mm Horizontal
6) Backfilled and compacted waste
Please note: Organised for the small Moxy Truck to be put on standby.
Chased up fittings. Lofts quarries arrived on site at aprox 8.30am with 3 x Truck and Dogs of 50/60mm ballast. Keysypicked up fittings, post and Uni strut etc from Barny at Adara after work.
|
|
03-AUG-2021 |
Andrew Keys |
1) Set up ready to commence the 3rd 90mm Horizontal
2) Pulled out 2 x 90mm coils and perforated ready for installation
3) Welded 20m of perforated pipe to a 100m length
4) Trenched and laid 120m of 90mm Horizontal
5) Installed 50/60mm Ballast
6) Backfilled and compacted waste
7) Washed Keysy's and Popz ute
8) Washed the small Moxy truck
Please note: Extremely wet on site, Rain on and off throughout the day.
Spoke to Reg about coming to site on Thursday to assist Surveying the installed Horizontals prior to the Landfill guys covering over them. |
|
02-AUG-2021 |
Andrew Keys |
1) Arrived to an extremely wet site this morning
2) Set up JB on the 37t excavator to continue trenching the 180m x 90mm Horizontal
3) Perforated 2 x 100m x 90mm Horizontals
4) Carted approx. 10 loads of fill to cover the excess waste from todays trenching works
5) Welded 1 x 90mm end cap, 1 x 90mm coupler
6) Trenched and laid approx. 120m of horizontal line
Note: Spoke to Deb RE fittings etc for MRL
Note: Spoke to Phil RE my proposed rostered time off 13th - 22nd |
|
31-JUL-2021 |
Andrew Keys |
1) Marked and perforated 90mm horizontal
2) Trenched and laid approximately 80m of 90mm Horizontal line
3) Installed 50/60mm ballast
4) Backfilled and track rolled
5) Removed the left over waste from yesterday - Please note this took Pops and Andy all day as the moxy truck we have is far too small
|
|
30-JUL-2021 |
Andrew Keys |
1) Marked and perforated 90mm pipe
2) Marked out each horizontal location
3) Trenched and laid 120m of 90mm horizonatl
4) Installed 50/60mm ballast
5) Backfilled and trackrolled waste
6) Loaded up day cover, lightly covered the days trench line
7) Commenced waste removal - Please note the Moxy truck we have on site is severely under sized and is going to cost us far to much time to achieve our daily targets
|
|
29-JUL-2021 |
Andrew Keys |
1) Mobilise to site
2) Meet with R.C to run over the proposed works at 7.00am
3) Meet with Oscar (Cleanaway) to sort out site contacts / permits etc
4) 14t Excavator / small moxy truck arrived on site at aprox 10.30 am
5) Loaded up 90mm coils on the coil trailer, relocated from the Gas plant up to the cell for construction
6) Pulled out 2 x 90mm coils ready for tomorrow
7) Cut in tracks on site to allow for easy access with light vehicles and our Moxy truck
8) Set up and flagged off the next few days works area
Plant / Equipment I:D's
Case 14t Excavator - PH.E.076
Dig bucket - P46-1-013
GP - P46-1-012
Mud - P46-1-011
37t Hydromek - OR089
Mud - OT81
450mm Dig - OT346
Moxy - SPH238 |