|
|
23-SEP-2022 |
Giovanni Bulgarelli |
Log created to capture the excavator that is on hire
No one on site - GB sick all week......payroll will do timesheets
No charge for Public holiday rental |
|
22-SEP-2022 |
Giovanni Bulgarelli |
Log created to capture the excavator that is on hire
No one on site - GB sick all week......payroll will do timesheets
No charge for Public holiday rental |
|
21-SEP-2022 |
Giovanni Bulgarelli |
Log created to capture the excavator that is on hire
No one on site - GB sick all week.....admin emailed Onetrak re: standown for today
payroll will do timesheets |
|
20-SEP-2022 |
Giovanni Bulgarelli |
Log created to capture the excavator that is on hire
No one on site - GB sick all week.....admin emailed Onetrak re: standown for today
payroll will do timesheets |
|
19-SEP-2022 |
Giovanni Bulgarelli |
Log created to capture the excavator that is on hire
No one on site - GB sick all week - not aware until Tuesday morning - therefore excavator was not stood down today
payroll will do timesheets |
|
10-SEP-2022 |
Giovanni Bulgarelli |
Jump start excavator for truck driver as it was off hired.
3hrs |
|
09-SEP-2022 |
Giovanni Bulgarelli |
Repair air and leachate line after Shamrock hit it.
2mtrs 90 pipe
2 90 sockets
500 ml 63 pipe
2 63sockets
3 1/2 hrs shamrock.
3 1/2 hrs cleaning site for cleanaway Z area
1 hrs cleaning excavator
9hrs work. |
|
08-SEP-2022 |
Giovanni Bulgarelli |
Trench 20 mtrs z403
Cut down z404 & z 405
Back filled z404
Covered hole (perf) that are showing so gas does not escape
Built up and covered perf on z406
Shamrock hit air line went over and put on squeeze off on line
Spoke with Vince about air and leachate line
Shamrock hit leachate line - put clamps on
Got diesel for excavator
Spoke to Rohad - excavator needed a jump start
Could not get down to connect lines as site was too wet |
|
07-SEP-2022 |
Giovanni Bulgarelli |
Z401 - completed and back on line
Back filled track rolled
Back filled 40 mtrs
3 x 90 Sockets
1 x T 90 x 90 Socket |
|
06-SEP-2022 |
Giovanni Bulgarelli |
Installed "J" trap and had to retrench 1 flow line 15 mtrs
Made up a "J" trap. |
|
05-SEP-2022 |
Giovanni Bulgarelli |
Made "J" trap installed and completed
Back filled 20 MTRS trench |
|
02-SEP-2022 |
Giovanni Bulgarelli |
Put up flagging around job site 3.5hrs
Repair leachate line 2 hrs
Left MRL around 10.30 am and went to Run Energy factory |
|
01-SEP-2022 |
Giovanni Bulgarelli |
Dug around Z342..cut & lowered well 3 mtr raise.
Trenched 40 mtrs Z342 installed pipe backfill
Escorted Lofts with rock on and off site
Made tracks on tip so ute could get close to work area
Got diesel and petrol
|
|
31-AUG-2022 |
Giovanni Bulgarelli |
1. Finished back filling z401 and lowering z401 cut pipe down. Reconnected.
2. Cut down z402
|
|
30-AUG-2022 |
Giovanni Bulgarelli |
1.Repairs - 3mtrs 160 pipe well Z317
2.Trench & back fill 35mtrs Z402
Repairs used:
1 x 160 Socket |
|
29-AUG-2022 |
Giovanni Bulgarelli |
Trenching and laying pipes for well Z401 |
|
26-AUG-2022 |
Giovanni Bulgarelli |
site pretty wet to work on
Landtrac have still not removed waste, attempted to lower a well but making a mess,
stopped work at 10 am and went to Clayton factory |
|
25-AUG-2022 |
Giovanni Bulgarelli |
no works onsite |
|
24-AUG-2022 |
Giovanni Bulgarelli |
Continue with flowline removal to lower wells
Went to Clayton factory pickup materials |
|
23-AUG-2022 |
Giovanni Bulgarelli |
Cut away flowlines from wells, Z341, 342,343
Removed flowlines from area |
|
17-AUG-2022 |
Giovanni Bulgarelli |
Pack up excavator for transport
Clean up pipework and take back to lay down area |
|
16-AUG-2022 |
Giovanni Bulgarelli |
Connected all leachate and air
Packed and secured header in place.
Posts and uni struts (still need 4 brackets)
|
|
15-AUG-2022 |
Giovanni Bulgarelli |
Connected air and leachate
Connected z header 200mm line
Locate air and leachate in the long grass |
|
13-AUG-2022 |
Giovanni Bulgarelli |
Connected air and leachate to new knock out pot and knock out pot 16. |
|
12-AUG-2022 |
Giovanni Bulgarelli |
Dragged air leachate lines to make it neat put some dirt under horizontals |
|
11-AUG-2022 |
Giovanni Bulgarelli |
ReConnected all 355 header line.
Reconnect hsp20 lateral header
Rock breaker was picked up.
|
|
10-AUG-2022 |
|
Trenched the pipe bed for the KOP.
Connected header to both KOPs.
Pulled all header line into place to be connected.
|
|
09-AUG-2022 |
Giovanni Bulgarelli |
Installed second KOP.
Uncovered and moved header line into place ready to connect up.
|
|
08-AUG-2022 |
Giovanni Bulgarelli |
Exposed header and Dug out KOP16.
Cut and capped 3 lateral headers
Isolated and Cut main header line to be moved.
Removed air and leachate lines
Installed second KOP.
Started rock breaking again to accommodate the bigger KOP.
|
|
05-AUG-2022 |
Giovanni Bulgarelli |
Finished excavating KOP holes.
Flagged around holes
Towed 200 pipe into place for lateral headers
|
|
04-AUG-2022 |
Giovanni Bulgarelli |
Excavated holes for KOP.
Positioned 355 header to tel he north
Started rock breaking after lunch |
|
03-AUG-2022 |
Giovanni Bulgarelli |
Dug out two KOP but found rock at 2.4meters. Ordered rock breaker for tomorrow,
Brought up pipe for leachate and air line.
Widened bed for header line.
Scraped 355 pipe and fittings
Backfilled KOP holes to make it safe for the night |
|
02-AUG-2022 |
Giovanni Bulgarelli |
Made a pad for KOP.
Made a bed for the lateral headers.
Tracked the excavator down to pick up the KOP. Collected fittings from the office |
|
01-AUG-2022 |
Giovanni Bulgarelli |
300 meters of bed made and path cleared for new header line.
Shamrock hit a well. 0 damage |
|
29-JUL-2022 |
Giovanni Bulgarelli |
Cleaned up pipe off cuts
Swapped over excavators
Knock outpot arrived
John checked his work order list |
|
28-JUL-2022 |
Giovanni Bulgarelli |
Fixed lp20r.
trenched flow line and back filled 50m
Continued looking for O2 leak.
Tracked excavator back to yard |
|
27-JUL-2022 |
Giovanni Bulgarelli |
Fix hit flow line. Continue looking for o2 leaks |
|
26-JUL-2022 |
Giovanni Bulgarelli |
Looked for O2 leak.
Fixed header we hit looking for leak |
|
25-JUL-2022 |
Giovanni Bulgarelli |
Refitted excavator track one track came out at 1pm |
|
22-JUL-2022 |
Giovanni Bulgarelli |
Looked for leak in header line - unable to find |
|
19-JUL-2022 |
Giovanni Bulgarelli |
Continued cleaning up pipe area
Loaded ute with pipe
Talked to Kate about header line
Spoke to Rob about jobs actioned and what is remaining to be done - copy of these attached in 'Photos' |
|
18-JUL-2022 |
Giovanni Bulgarelli |
Started to fixed and connect LP20R to header until the rain started at 8 am
Continued the day by moving pipe next to power station fence & stacking bentonite |
|
15-JUL-2022 |
Giovanni Bulgarelli |
Repaired damaged header line
Finished joining LP20R at sump & line to header, still need to join on to header with saddle.
Parts used:
Header:
1 x 160 5mtr pipe
2 x 160 sockets
LP20R
3 x 90sockets
1 x 90 x 63 reducer
1x 63 elbow |
|
14-JUL-2022 |
Giovanni Bulgarelli |
Continued LP20R line
Scrapped and cut pipe will connect tomorrow
Line M538 was hit causing air leak. Exposed area to find leak. Discovered header line was also hit, exposed area and capped off flow line
Parts used:
1 x 90 Socket
1 x 90 Hard Cap |
|
13-JUL-2022 |
Giovanni Bulgarelli |
Finished trenching PO20R
Trenched 35mtrs (Road Crossing). There was rubbish 100mm below surface. Lantrak said to put aside and they would take away.
Installed pipe, back filled, track rolled with dry clay
|
|
12-JUL-2022 |
Giovanni Bulgarelli |
Continued trenching from LP20R to header line
Trenched 30 mtrs
Digging was hard
Back filled, track rolled, joined pipe 1 x 90 socket
Found more 90mm pipe on site to continue. |
|
11-JUL-2022 |
Giovanni Bulgarelli |
Had issues with excavator but got it started around 9.30 am
Walked excavator from KOP41 to LP20R
Put up flagging around job area and trenched 30 metres from LP20R
Back filled and track rolled. |
|
08-JUL-2022 |
Giovanni Bulgarelli |
Moved air and leachate line near sump 41 from side of road to higher ground and covered horizontal lines that had perforations showing |
|
07-JUL-2022 |
Giovanni Bulgarelli |
Clean up rock from around flare
|
|
06-JUL-2022 |
Giovanni Bulgarelli |
Unable to trench LP20R as Ritchie from Lantrak advised this was not possible as Lantrak trucks would be using the road.
Rob Barton asked for the mud to be cleaned up in the flare compound |