MRL Leachate Collection System
Cleanaway Waste Management Ltd
Melbourne Regional Landfill
1100-1152 Christies Rd, Ravenhall, Victoria 3023 Australia

Complete
 
Date
Document Type
Document
 
Issued for Construction Drawing Set  (1 Document)  
06-APR-2023 Issued for Construction Drawing Set Doc
Leachate Collection System Installation

Run Energy will:

  • Install leachate sump headworks
  • Trench, weld and lay leachate line
  • Weld and lay air line
  • Install air and leachate risers
  • Install in accordance with attached design drawing:
    • Melbourne Regional Landfill - Leachate System Installation - Dwg 015-DN-025

Details:

Item Quantity/Size Installation Notes General Arrangement Drawing Reference
Leachate line 1,760 m x 200 mm PN10  Weld and lay on ground surface as per design drawing N/A
Road crossing 12 m x 450 mm PN10 Trench weld and lay road crossing. Use class 2 road base for backfill and compact as required. RE-LFG- 187 - Road Crossing
Air line 1,850 mm x 63 mm PN16 Weld and lay on ground surface as per design drawing N/A
Air and leachate risers 7 x 63 mm PN16 Complete valve train and frame RE-LFG-143 - Air & Leachte Riser Manifold
  • No variations
Pump Supply

Run Energy will supply:

Item Quantity/Unit
Airwell BF8009A (200m x 0.9m) sump pump on skids 3
Solar controller 3
Cable kit 3 x 75 m
Seal cap 3 x 540 mm ID
Air regulator/cycle counter 3
Exhaust pipe/support pole  3
Air pump kit 3
Liquid level tube arrangement 3
  • No variations
Pump Installation

Run Energy will:

  • Assemble pumps offsite
  • Install pumps
  • Install liquid level tube arrangements
  • Install stainless steel and communication supporting cables
  • Install control box complete with air regulator and cycle counter
  • Install lids and seal caps
  • Install exhaust/support poles
  • Connect to leachate collection system
  • Commission pumps

Details:

Item Quantity/Details
Pump 3 x Airwell BF8009A (200m x 0.9m) sump pump on skids
Connection to leachate collection system Air and leachate risers at each location
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1 Leachate Line - 1,760m x 200mm Lay   Yes  
2 Road Crossing - 12m  x 450mm Trench   Yes  
3 Air Line - 1850m x 63mm weld and lay   Yes  
4 Air & Leachate Risers - 7 x 63mm   Yes  
5 Pump Supply - BF8009A x 3    
6 Variation No.11325 - Flow Meter200mm   Yes  
7 Variation No.11345 - Additional Resources Leachate Line   Yes  
8 Variation No.11326 - Air Relief and 63mm Air Line   Yes  
9 Variation No.11308 - Air Relief and 63mm Air Line   Yes  
10 Variation No.11421 - Cell 1 Pump separation from leachate line    
 
Date Issued
Equipment Type
Equipment Serial ID
 
No Record records found
 
Date
Team Lead
Work Summary
 
13122 - MRL Leachate Collection System  (131 Daily Log records) 
09-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
06-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
05-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
04-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire

As per Log for Job No.13059 - Crew were rained off @ MRL 
Onetrak have agreed to stand down excavator OR083 @ 50% for today
03-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire

As per Log for Job No.13059 - Crew were rained off @ MRL 
Onetrak have agreed to stand down excavator OR083 @ 50% for today
02-OCT-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
29-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
28-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
27-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
26-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
25-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
22-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
21-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
20-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
19-SEP-2023 Reg Blair No works completed on this job today
Log created to capture excavator hire
18-SEP-2023 Reg Blair Variation No.1308
Modified 110mm stub flanges for flow metre
Installed flow metre on 200mm leachate line 
Pinned 90mm leachate line over other side of road
Pops 5hrs
Johnny 5hrs
Craig weir 5hrs

Materials used:
2x 200/160 EF Reducers
2x 160/110 reducers
6x 110mm EF Sockets
4x 110mm stud flanges
2x dn100 butterfly valves
15-SEP-2023 Reg Blair VAR#1752
Ran 90mm line under road and tee into 200mm leachate line 
Gathered and modified parts for flow metre install
Pops 9hrs
Johnny 6hrs
Craig weir 6.5

Materials used :
1x 200/90 EF T
1x 90mm ball valve
2x 90mm transitions
1x 110/90 ef reducer
1x 90mm 90/elbow
1x 90mm EF T
4x 90mm ef sockets
1x 110 end cap

Excavator 5 hrs
14-SEP-2023 Reg Blair Variation No.1308

Tapped leachate line in at gas station end 
Flipped 1way valve and fixed leak 
Installed 200mm butterfly valve for isolation and to install flow metre
13-SEP-2023 Reg Blair Variation No.1308

Continued with 200mm leachate line around the pond
Removed and capped old flow metre line
Connected 200mm leachate line at ponds end
Cleaned and removed build up from flow metre and unsiezed both 90mm ball valves
Pops 10hrs
Johnny 10hrs
Craig weir 7.5hrs

Materials used 
1x 160/200 ef reducer
1x 200mm ef 90/elbow
2x 200mm ef sockets
1.7m 200mm pipe

Excavator 8hrs
12-SEP-2023 Reg Blair Variation No.1308

Pulled pipe into place and started the pinning and welding process.

Materials used 
1x 200mm EF 90/elbow
1x 200mm EF Socket

Excavator 8hrs
11-SEP-2023 Reg Blair Relocated stage 4 header line pipework out of way for clean away to start rubbish filling in area.
Pops 3hrs 

Variation No.1308
Started making a shelf for 200mm leachate line to sit on.
Pulled pipe through under new road and towards ponds 
Pops 7hrs
Johnny 10 hrs 
Craig weir 10 hrs 

Excavator  8hrs
08-SEP-2023 Reg Blair Variation No.1308

Butt welded 240m of 200mm pipe into 4x 60m lengths

Excavator 8hrs
07-SEP-2023 Reg Blair No works completed on this job
Log created to capture hire equipment
06-SEP-2023 Reg Blair Variation No.1308
Moved pipe and container from stage 2 to the power station 
Excavator 3hrs
05-SEP-2023 Reg Blair No works completed on this job
Log created to capture hire equipment
04-SEP-2023 Reg Blair No works completed on this job
Log created to capture hire equipment
01-SEP-2023 Reg Blair Variation No.1710
Remove 160mm from road crossing and install 200mm leachate line ,Connected 200mm leachate line to system

Materials used
6x 200mm ef sockets
1x 200mm 90/elbow
1x 200mm ef T
1x 90/110 ef reducer
2x 63mm ef sockets
31-AUG-2023 Reg Blair VAR#1710
Assembled, cut in and welded pressure tester
Installed 3of3 breather branch awaiting breather valves
Pressure tested 200mm leachate line successfully 

Materials used:
1x 200mm T
3x 200mm EF Sockets

Pops - personal leave - 7003Const - admin has processed this timesheet
30-AUG-2023 Andrew Keys VAR#1710
Changed over excavator off hire 8t and 14t on hire
Capped 200mm leachate line ready for pressure test
Cut and welded breather T's in 200mm leachate line x3
Pops 9hrs
Dayne 9hrs
Craig weir 10.5hrs

Materials used:
1x 200mm EF Socket
1x 200mm end cap
3x 200/90 EF T's
2x 90/63 EF Reducer
1m 63mm pipe
2x 63mm male transition 
1m 90mm pipe
2x 90mm EF sockets

29-AUG-2023 Andrew Keys No works completed on this job
Log created to capture hire equipment
28-AUG-2023 Andrew Keys No works completed on this job
Log created to capture hire equipment
25-AUG-2023 Rob Barton No works completed on this job
Log created to capture hire equipment
24-AUG-2023 Rob Barton No works completed on this job
Log created to capture hire equipment
23-AUG-2023 Rob Barton No works completed on this job
Log created to capture hire equipment
22-AUG-2023 Rob Barton No works completed on this job
Log created to capture hire equipment
21-AUG-2023 Rob Barton Transported and Unloaded delivery truck
Assessed stage 4 header line relocation in shamrock area 

Pinned stage 1 leachate line (160mm) after moving it on friday VAR#1308

Excavator 4hrs
18-AUG-2023 William (Daniel) Williams Variation No.1681
Move leachate line and Reconnected 

Materials used: 
2x 160mm EF Sockets
2x 63mm EF Sockets

Excavator 8hrs
17-AUG-2023 William (Daniel) Williams No works completed on this job 
Log created to capture the hire equipment
16-AUG-2023 William (Daniel) Williams No works on this job
Log created to capture hire equipment
15-AUG-2023 William (Daniel) Williams No works under this job.
Log created to capture the excavator hire
14-AUG-2023 William (Daniel) Williams No one worked on this job
Log created to capture the excavator hire 
11-AUG-2023 William (Daniel) Williams Uncoil 63mm pipe 
Lay air line and weld together and put in place
Back fill areas that need filling and tidy up

Escorted truck to pick up big excavator
Johnnie 1hr - J#13122...has been added to John's timesheet 
John has a total of 5 x hours to 13122

VAR#1547
10-AUG-2023 William (Daniel) Williams Trench in Winslow road crossing,
Lay leachate and air lines 
Install flow metre and valve set up,
Backfill and tidy up
Uncoil 63mm pipe and lay in  place

Variation No.1547

Excavator OR086 off hired as of COB today
09-AUG-2023 Reg Blair Reg Blair 
VAR#1547



08-AUG-2023 Reg Blair Make up flow meter with stub flanges and pipe
Buttwelded 4 x 20m length 200mm pipe

VAR#1325
07-AUG-2023 Reg Blair Cleaned up area after road crossing completion from Friday
Johnnie 5hrs
Pops 5hrs
VAR#1547

Butt welded feed for leachate line 
Johnnie 2hrs
Pops 2hrs
No Varaition  - relates to main job

Repaired pipework from tonka truck flattening it. Fittings used for repair :40m of 200mm poly pipe and 2x200mm EF sockets.
Johnnie 3hrs
Pops 3hrs
VAR#1660

04-AUG-2023 Giovanni Bulgarelli Road crossing 
25 hrs trench sleeved 200 leachate line
Used 1 x200mm socket
Back filled and track rolled
03-AUG-2023 Giovanni Bulgarelli Trench 200mm leachate line


Excavator OR102 broke down...crew could not work for 6 hours.
They cleaned vehicles/tidied site etc.
02-AUG-2023 Reg Blair Johnnie 
Pops 



01-AUG-2023 Reg Blair continue on  with road Crossing entrances
Johnnie 
Pops 



Result Pages:  1  2  3    
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
15-MAR-2024 Melbourne Regional Landfill Job GCS As-Built As built 13122 13122 Dwg
No
Yes
No
The search criteria for this report references restricted fields.
Yes
Unable to display report. You do not have sufficient permission.
Russell Clarke
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.