09-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
06-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
05-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
04-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire
As per Log for Job No.13059 - Crew were rained off @ MRL
Onetrak have agreed to stand down excavator OR083 @ 50% for today |
|
03-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire
As per Log for Job No.13059 - Crew were rained off @ MRL
Onetrak have agreed to stand down excavator OR083 @ 50% for today |
|
02-OCT-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
29-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
28-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
27-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
26-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
25-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
22-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
21-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
20-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
19-SEP-2023 |
Reg Blair |
No works completed on this job today
Log created to capture excavator hire |
|
18-SEP-2023 |
Reg Blair |
Variation No.1308
Modified 110mm stub flanges for flow metre
Installed flow metre on 200mm leachate line
Pinned 90mm leachate line over other side of road
Pops 5hrs
Johnny 5hrs
Craig weir 5hrs
Materials used:
2x 200/160 EF Reducers
2x 160/110 reducers
6x 110mm EF Sockets
4x 110mm stud flanges
2x dn100 butterfly valves
|
|
15-SEP-2023 |
Reg Blair |
VAR#1752
Ran 90mm line under road and tee into 200mm leachate line
Gathered and modified parts for flow metre install
Pops 9hrs
Johnny 6hrs
Craig weir 6.5
Materials used :
1x 200/90 EF T
1x 90mm ball valve
2x 90mm transitions
1x 110/90 ef reducer
1x 90mm 90/elbow
1x 90mm EF T
4x 90mm ef sockets
1x 110 end cap
Excavator 5 hrs |
|
14-SEP-2023 |
Reg Blair |
Variation No.1308
Tapped leachate line in at gas station end
Flipped 1way valve and fixed leak
Installed 200mm butterfly valve for isolation and to install flow metre |
|
13-SEP-2023 |
Reg Blair |
Variation No.1308
Continued with 200mm leachate line around the pond
Removed and capped old flow metre line
Connected 200mm leachate line at ponds end
Cleaned and removed build up from flow metre and unsiezed both 90mm ball valves
Pops 10hrs
Johnny 10hrs
Craig weir 7.5hrs
Materials used
1x 160/200 ef reducer
1x 200mm ef 90/elbow
2x 200mm ef sockets
1.7m 200mm pipe
Excavator 8hrs |
|
12-SEP-2023 |
Reg Blair |
Variation No.1308
Pulled pipe into place and started the pinning and welding process.
Materials used
1x 200mm EF 90/elbow
1x 200mm EF Socket
Excavator 8hrs |
|
11-SEP-2023 |
Reg Blair |
Relocated stage 4 header line pipework out of way for clean away to start rubbish filling in area.
Pops 3hrs
Variation No.1308
Started making a shelf for 200mm leachate line to sit on.
Pulled pipe through under new road and towards ponds
Pops 7hrs
Johnny 10 hrs
Craig weir 10 hrs
Excavator 8hrs |
|
08-SEP-2023 |
Reg Blair |
Variation No.1308
Butt welded 240m of 200mm pipe into 4x 60m lengths
Excavator 8hrs
|
|
07-SEP-2023 |
Reg Blair |
No works completed on this job
Log created to capture hire equipment |
|
06-SEP-2023 |
Reg Blair |
Variation No.1308
Moved pipe and container from stage 2 to the power station
Excavator 3hrs |
|
05-SEP-2023 |
Reg Blair |
No works completed on this job
Log created to capture hire equipment |
|
04-SEP-2023 |
Reg Blair |
No works completed on this job
Log created to capture hire equipment |
|
01-SEP-2023 |
Reg Blair |
Variation No.1710
Remove 160mm from road crossing and install 200mm leachate line ,Connected 200mm leachate line to system
Materials used
6x 200mm ef sockets
1x 200mm 90/elbow
1x 200mm ef T
1x 90/110 ef reducer
2x 63mm ef sockets |
|
31-AUG-2023 |
Reg Blair |
VAR#1710
Assembled, cut in and welded pressure tester
Installed 3of3 breather branch awaiting breather valves
Pressure tested 200mm leachate line successfully
Materials used:
1x 200mm T
3x 200mm EF Sockets
Pops - personal leave - 7003Const - admin has processed this timesheet |
|
30-AUG-2023 |
Andrew Keys |
VAR#1710
Changed over excavator off hire 8t and 14t on hire
Capped 200mm leachate line ready for pressure test
Cut and welded breather T's in 200mm leachate line x3
Pops 9hrs
Dayne 9hrs
Craig weir 10.5hrs
Materials used:
1x 200mm EF Socket
1x 200mm end cap
3x 200/90 EF T's
2x 90/63 EF Reducer
1m 63mm pipe
2x 63mm male transition
1m 90mm pipe
2x 90mm EF sockets
|
|
29-AUG-2023 |
Andrew Keys |
No works completed on this job
Log created to capture hire equipment |
|
28-AUG-2023 |
Andrew Keys |
No works completed on this job
Log created to capture hire equipment |
|
25-AUG-2023 |
Rob Barton |
No works completed on this job
Log created to capture hire equipment |
|
24-AUG-2023 |
Rob Barton |
No works completed on this job
Log created to capture hire equipment |
|
23-AUG-2023 |
Rob Barton |
No works completed on this job
Log created to capture hire equipment |
|
22-AUG-2023 |
Rob Barton |
No works completed on this job
Log created to capture hire equipment |
|
21-AUG-2023 |
Rob Barton |
Transported and Unloaded delivery truck
Assessed stage 4 header line relocation in shamrock area
Pinned stage 1 leachate line (160mm) after moving it on friday VAR#1308
Excavator 4hrs |
|
18-AUG-2023 |
William (Daniel) Williams |
Variation No.1681
Move leachate line and Reconnected
Materials used:
2x 160mm EF Sockets
2x 63mm EF Sockets
Excavator 8hrs |
|
17-AUG-2023 |
William (Daniel) Williams |
No works completed on this job
Log created to capture the hire equipment |
|
16-AUG-2023 |
William (Daniel) Williams |
No works on this job
Log created to capture hire equipment |
|
15-AUG-2023 |
William (Daniel) Williams |
No works under this job.
Log created to capture the excavator hire |
|
14-AUG-2023 |
William (Daniel) Williams |
No one worked on this job
Log created to capture the excavator hire
|
|
11-AUG-2023 |
William (Daniel) Williams |
Uncoil 63mm pipe
Lay air line and weld together and put in place
Back fill areas that need filling and tidy up
Escorted truck to pick up big excavator
Johnnie 1hr - J#13122...has been added to John's timesheet
John has a total of 5 x hours to 13122
VAR#1547
|
|
10-AUG-2023 |
William (Daniel) Williams |
Trench in Winslow road crossing,
Lay leachate and air lines
Install flow metre and valve set up,
Backfill and tidy up
Uncoil 63mm pipe and lay in place
Variation No.1547
Excavator OR086 off hired as of COB today |
|
09-AUG-2023 |
Reg Blair |
Reg Blair
VAR#1547
|
|
08-AUG-2023 |
Reg Blair |
Make up flow meter with stub flanges and pipe
Buttwelded 4 x 20m length 200mm pipe
VAR#1325
|
|
07-AUG-2023 |
Reg Blair |
Cleaned up area after road crossing completion from Friday
Johnnie 5hrs
Pops 5hrs
VAR#1547
Butt welded feed for leachate line
Johnnie 2hrs
Pops 2hrs
No Varaition - relates to main job
Repaired pipework from tonka truck flattening it. Fittings used for repair :40m of 200mm poly pipe and 2x200mm EF sockets.
Johnnie 3hrs
Pops 3hrs
VAR#1660
|
|
04-AUG-2023 |
Giovanni Bulgarelli |
Road crossing
25 hrs trench sleeved 200 leachate line
Used 1 x200mm socket
Back filled and track rolled |
|
03-AUG-2023 |
Giovanni Bulgarelli |
Trench 200mm leachate line
Excavator OR102 broke down...crew could not work for 6 hours.
They cleaned vehicles/tidied site etc. |
|
02-AUG-2023 |
Reg Blair |
Johnnie
Pops
|
|
01-AUG-2023 |
Reg Blair |
continue on with road Crossing entrances
Johnnie
Pops
|