- Trench, weld and lay main header line
- Weld and lay main header line
- Repair salvaged main header line
- Weld and lay air line
- Relocate condensate tank
- Install knock-out pot
- Relocate Airwell pump
Item |
Quantity/Size |
Installation Notes |
Main header line (trench) |
80 m x 200 mm PN10 |
Trench at road crossings |
Main header line (surface lay) |
705 m x 200 mm PN10 |
Install from existing main header line on cell boundary (stage 1) to knock-out pot near the power station
Install securing mounds along main header line at 20 m – 25 m intervals
|
Repair salvaged main header line |
353 m x 200 mm PN10 |
Existing main header line (353 m x 200 mm ) has been salavaged for reuse – repair sections (butt weld) as required
Remaining 432 m pipework required for works will be supplied
|
Air line |
785 m x 40 mm PN16 |
Replace existing air line |
Condenstate tank |
1 x 10,000 L (approx.) |
Relocate 75 m north east outside area B2 boundary |
Knock-out pot |
1 x 500 mm x 200 mm |
Install at new location of condesate tank |
Airwell pump |
1 x 1000 mm |
Remove from existing knock-out pot and install in new knock-out pot |
Ramp on grade from stage 1 to condensate tank location will be constructed by Boral – any works to alter ramp will incur additional costs
Stage 1 main header line was installed by LMS – location/aligment unknown
Works to locate main header line will be charged at hourly rate of $290.70 and billed separately
|