11454
MRL Cell 4A Leachate & Air
Cleanaway Waste Management Ltd
Melbourne Regional Landfill
1100-1152 Christies Rd, Ravenhall, Victoria 3023 Australia

Complete
Leachate Collection System Installation
  • Trench, weld and lay leachate line
  • Weld and lay leachate line
  • Weld and lay air line
  • Install safety flagging along pipe route
  • Install isolation valves
  • Install valve pit
  • Install air and leachate risers
  • Install in accordance with the attached drawing
Item Quantity/Size Installation Notes
Leachate line 25 m x 110 mm PN10
  • Trench, weld and lay leachate lines across access road to transfer leachate from leachate sumps in cell 4A.
  • Pipework will have 50 mm of bedding sand with 150 mm of cover sand
Pipe sleeve  25 m x 355 mm PN10 
  • Install through road crossing to protect air and leachate line
  • Pipe sleeve to be provided by the customer
Safety flagging  1,200 m 
  • Install 140 star pickets with safety caps and string flagging on top of star pickets.
  • Underground locator to clear route.
Leachate line 1,169 m x 110 mm PN10
  • Weld and lay along route indicated on attached concept design sketch
Air line 1,194 m x 63 mm PN12.5
  • Weld and lay along route indicated on attached concept design sketch

 

Air and leachate risers 4 m x 63 mm PN12.5 Connect leachate pump  to the leachate collection system
Unistrut setup complete 2 Install at each leachate sump to secure air and leachate risers
Isolation valve pit 1 x 500 mm To house isolation valves
Isolation valve 1 1 x 4" stainless Install on leachate collection line on cell 3B boundary
Isolation valve 2 1 x 2" stainless Install on air line on cell 3B boundary
  • No variations
Pump Installation

Run Energy will:

  • Assemble pump offsite
  • Install pump
  • Install liquid level tube arrangement
  • Install stainless steel and communication supporting cables
  • Install control box complete with air regulator and pulse counter
  • Install seal caps
  • Install exhaust/support pole
  • Connect to leachate collection system
  • Commission pump

Details:

Item Quantity/Details
Pump
  • Pumps supplied from Cleanaway inventory
  • Install pumps into new sumps in cell 4B (ID's to be confirmed)
    • 1 x Airwell 8" with skid
    • 1 x Airwell 6" with skid
Connection to leachate collection system Connect pumps to leachate and air risers at each sump
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1    
2    
3    
4    
5    
6    
7    
8    
9    
10    
 
Date Issued
Equipment Type
Equipment Serial ID
 
11454  (36 Record records) 
11-NOV-2018   126689
11-NOV-2018 EF Welder 170603320
11-NOV-2018   565075
11-NOV-2018 Personal Gas Monitor KA416-1056664
07-NOV-2018 EF Welder 170603320
07-NOV-2018   126689
07-NOV-2018 Personal Gas Monitor KA416-1056664
07-NOV-2018   565075
06-NOV-2018 EF Welder 170603320
06-NOV-2018   126689
06-NOV-2018 Personal Gas Monitor KA416-1056664
06-NOV-2018   565075
01-NOV-2018 EF Welder 170603320
01-NOV-2018   126689
01-NOV-2018   565075
01-NOV-2018 Personal Gas Monitor KA416-1056664
31-OCT-2018   126689
31-OCT-2018 EF Welder 170603320
31-OCT-2018   565075
31-OCT-2018 Personal Gas Monitor KA416-1056664
30-OCT-2018   126689
30-OCT-2018 EF Welder 170603320
30-OCT-2018   565075
30-OCT-2018 Personal Gas Monitor KA416-1056664
29-OCT-2018   126689
29-OCT-2018 Personal Gas Monitor KA416-1056664
29-OCT-2018   565075
28-OCT-2018   126689
28-OCT-2018 Personal Gas Monitor KA416-1056664
28-OCT-2018   565075
26-OCT-2018   126689
26-OCT-2018 Personal Gas Monitor KA416-1056664
26-OCT-2018   565075
25-OCT-2018   126689
25-OCT-2018 Personal Gas Monitor KA416-1056664
25-OCT-2018   565075
 
Date
Team Lead
Work Summary
 
No Daily Log records found
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
30-MAR-2020 Melbourne Regional Landfill Job GCS As-Built 20190925_MRL_SITE ASBUILT_REV Y 11454 11454 Dwg
No
No
No
No
Russell Clarke
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.