02-NOV-2020 |
|
Drove to Kimbriki picked up tools and generator the went to Erskine Park.
Exposed leaking leachate line.
Removed 50mm compression fitting cleaned it up and reinstalled.
Back filled exposed area. |
|
19-OCT-2020 |
|
Filled in more around KOP and tidied area.
Dug down 1m on well 75 and bentonite well and reseal.
Packed up all hire equipment and cleaned site office for off hire.
GPS new J Traps and well station and leachate line.
(Excavator 231 will have daily charge accidently clicked on no daily charge).
Also unsure whether all the Coats stuff will have daily charge as it was off hired first thing in the morning. |
|
18-OCT-2020 |
|
Completed site variations.
Finished tidying all work areas. |
|
17-OCT-2020 |
|
Back fill J Traps, tidy up area |
|
16-OCT-2020 |
|
Dug and installed J Traps on e manifold.
Tidy up batter.
( Add tilt bucket to hire equipment log please) |
|
15-OCT-2020 |
|
Continued back filling trenches and cleaning up.
Tidied up rocks on batter.
|
|
14-OCT-2020 |
|
Continued back filling trenches and cleaning up. |
|
13-OCT-2020 |
|
Continued back filling trenches and cleaning up. |
|
12-OCT-2020 |
|
Backfill, compact and tidy up. |
|
11-OCT-2020 |
|
Back fill where 355 header line was and reshape batter.
Clean utes. |
|
10-OCT-2020 |
|
Expose 355 Header line through road crossing, remove Header line and air line to drop the pipe by 300mm. Sand up and backfill and reinstate road.
Continue backfilling trench where the 355 pipe was. |
|
09-OCT-2020 |
|
Sand and Back fill 355mm main gas line
130m.
Start to backfill trench from where the 355 line was pulled out of. |
|
08-OCT-2020 |
Richard Andrews |
Richard flew home.
Mitchell and kieran sanded and backfilled 355mm gas main 100m
Exposed, trenched and hooked up sump to 90mm gas main. Sanded and backfilled. |
|
07-OCT-2020 |
Richard Andrews |
Expose around tie in point, dig out last bit of trench and tie in header line.
GPS works. |
|
06-OCT-2020 |
Richard Andrews |
Weld and lay flow lines to wells G64 and G65 and connect to new header.
Make, dig and install 1 x J trap.
Organise and pick up fittings for tie in.
Run loads of sand down to tie in point.
Off hire SPH197 14t excavator and tilt bucket.
Excavator OH24308 swapped out for SPH175.
Order and receive 3 truck and dogs of pipe bedding.
Dump truck not running, had someone onsite to repair.
|
|
05-OCT-2020 |
Richard Andrews |
Weld and lay air from G64 down to tie in point.
Cut and remove 355mm header and lay down to tie in point.
Back filling near exit road.
Reinstate drain near flare.
Trench from G65 and G64 up to new header.
Sand up pipe from barra trap to H073.
Back filling and clean up from KOP to H073.
Start building fill around well stations. |
|
04-OCT-2020 |
Richard Andrews |
Shut down and cap 355mm header near flare, cut and cap air line at same location.
Lay out 11 straight lengths of 315mm and weld together with ef couplers.
Cut and remove exposed header line.
Weld and Lay 315mm header from well G64 down to flare.
Pull out 63mm coils.
Sand up pipe from KOP to well 9.
|
|
03-OCT-2020 |
Richard Andrews |
Finish exposing header.
Connect flow lines to E station and bring online.
Trench across road and down to flare.
Lay header and air across road.
Back fill road crossing. |
|
02-OCT-2020 |
Richard Andrews |
Install air and leachate at KOP so ops can reinstall pump.
Join header lengths together between barra trap and road.
Cut and remove E station and install at new location.
Tie E station into new header.
Shut down and tie in header, cap end. E station back online.
Lay air line from barra trap to road.
Start connecting flow lines back to E station.
Expose tie in point.
Continue exposing header.
Pick up 1GE6SH from mechanics.
Pick up fittings from GF and Kenkar. |
|
01-OCT-2020 |
Richard Andrews |
Continue exposing header.
Back fill and clean up around well 10.
Cut and cap air and header near G64.
Run loads of sand to trench area.
Remove header and air line.
Lay header from Barra trap to H073.
Work out fittings required for job and pick up from GF.
Work out pipe needed to finish job. |
|
30-SEP-2020 |
Richard Andrews |
Continue exposing header line, getting very deep and close to main exit rd.
Pull out coils and lay 90mm leachate from KOP to well 10, tie in new leachate line to existing.
Install risers at barra trap.
Make J trap, expose flow line at well 10, trench weld and lay flow line from header to well 10, dig and install J trap. Tie in.
Trench past E station and up to 2nd rd crossing near G64.
Build pad for E station, expose flow lines and trench up to new pad.
Expose E station.
Expose header near flare, header not adding up with drawing provided. |
|
29-SEP-2020 |
Richard Andrews |
Continue exposing 315mm header past E station.
Connect remaining 4 wells to D station and open valves.
Trench from road crossing towards new E station location.
Weld and lay 315mm header and air from D station to barra trap.
Weld and lay 90mm leachate across road.
Make, dig, install and connect barra trap.
Back fill and clean up road crossing.
|
|
28-SEP-2020 |
Richard Andrews |
Tie in D station to header line and cap end of line.
Dig and install 6 x J traps.
Connect 2 flow lines to traps and manifold.
Dig and install KOP.
Shut down, tie in KOP and new header line.
D station back online.
Trench from D station to road crossing. |
|
27-SEP-2020 |
Richard Andrews |
Day off. |
|
26-SEP-2020 |
Richard Andrews |
Shut down, cut and cap header near E station.
Weld and lay 315mm main header and 63mm air line from tie in point to D station.
Expose flow lines up to new D station location.
Expose 160mm lateral header, cut and relocate D station.
Remove header from D station to road.
Make J traps. |
|
25-SEP-2020 |
Richard Andrews |
Pump out KOP into water trailer and empty on landfill.
Cut and cap air line.
Trench from tie in point to D station.
Remove existing header and air from tie in point to D station.
Expose flow lines at D station.
Keep exposing header towards E station.
Extreme winds throughout the day and rain in late afternoon.
Receive dump truck and excavator. |
|
24-SEP-2020 |
|
Richard and Craig arrive on site, run through works with Ben.
Continue exposing 315mm header.
Shut down at 1:30pm.
Cut and cap header at C and D station.
Turn system back on at 2:45pm.
Continue exposing header.
Pick up 63mm end caps to cap air line.
Receive fittings and additional excavator. |
|
23-SEP-2020 |
|
Continued exposing main header line. Past road crossing etc. |
|
22-SEP-2020 |
|
Continue exposing main header line. |
|
21-SEP-2020 |
|
Expose main header line and KOP.
Expose around tie in point.
Survey new header line and peg it out.
|
|
20-SEP-2020 |
|
Day off.
|
|
19-SEP-2020 |
|
Continued to expose main header line.
|
|
18-SEP-2020 |
|
Continue exposing main header line, benched out etc. |
|
17-SEP-2020 |
|
Exposing existing header line, benching out current trench. roughly 2.5m deep at current point. |
|
16-SEP-2020 |
|
Start day off brief chat with Chris and Paul regarding site works.
Clean container, search through tools etc.
Set up office, toilet, genie and relocate container.
Purchase tools Sydney tools
Buckets id.
Mud bucket B960
300 B623
600 B617
( once buckets are added just let me know and ill add them to following log) |