19-APR-2023 |
|
OHS meeting in the morning.
Marcus went to bingo to pick up 12x 90 couplers.
2x6m lengths of 90
Raised 6x 63mm flow lines 3 meters
raised 6x 90mm J traps 3 meters
Raised 160mm vaccumm line 4 meters
Raised well directly behind C station 4 meters
Re assembled pump with new 40 and 16mm lines.
pump installed at 15.57m
Bottom plate on the biscuit was too big for the pipe.
biscuits just taped on KOP4
didnt have time to fix properly as chris had already left and site closed in 20 minutes and we didnt have the fittings to do so.
Pump however was in and operational. |
|
27-MAR-2023 |
Andrew Dawson |
Waited on site to talk to Chris about plans to reinstall knockout pot
Chris came to the conclusion waste would not be at a level to reinstall that day
Couple hours of rain first thing in the morning
Cleaned up work area
Cleaned up excavator |
|
26-MAR-2023 |
Andrew Dawson |
Drove to bingo to pickup 40mm coil and stainless steel cable
Filled in around risers with sand and dirt, had to track a little far to grab
Put spacers and straighted up lines while filling
Attatched stainless steel cable to pump with D shackle
Drove to jonesys to pickup 16mm airline and bubbler tube |
|
25-MAR-2023 |
Andrew Dawson |
Welded screw caps on J traps
Connected 6 J traps to flowlines
Backfilled hole
Raised 6 flowlines 3m and capped (Chris mentioned to just raise them and not to worry about hooking them up as they will fill around it and when we are available to raise again straight after)
Started putting sand around risers |
|
24-MAR-2023 |
Andrew Dawson |
Picked up pipe from bingo as pipe meant for Erskine was delivered there.
Made up 6 J traps
Cut 160mm header going to C manifold and capped
Cut C manifold
Dug hole for J trap
Hole was just dirt, went as deep as excavator could : 4.2m
Went another trenching bucket wide
Started hooking up J traps |
|
23-MAR-2023 |
Andrew Dawson |
Drove to pick up squeeze off from Elizabeth drive, delay on travel due to crash.
Excavator arrived 9.30
Raised 160mm 6m on KOP4
Couldn't raise 63mm due to no pipe on site
Exposed around C station in preparation to raise
Pipe arrived on site 3.30
Raised leachate and air on KOP4
|
|
02-MAR-2023 |
Andrew Dawson |
Out of scope works:
Sika flex to seal up lp04 90mm riser |
|
27-FEB-2023 |
Andrew Dawson |
Waiting for fitting via uber
Repaired damaged flowline and saddle |
|
13-FEB-2023 |
Andrew Dawson |
Exposed 2 points of header line
1 near C station, 1 near kop6
Squeezed off airline at both ends and capped off
Airline had leak between those two points
GPS'd all wells and flowlines
Cleaned up excavator ready to be picked up.
Excavator off hired as of COB 13.02.2023 |
|
11-FEB-2023 |
Andrew Dawson |
Cut wellhead off h075
Raise well 4m with plain pipe and endcap.
Cap 63mm flowline
|
|
10-FEB-2023 |
Andrew Dawson |
2 well heads
Poles and struts for 4 stand alones
160-63 clamp with struts on 3 wells
Tied into E station
Backfilled around E station
|
|
09-FEB-2023 |
Andrew Dawson |
Trenched to H075 & 9
Saddled into 225 and 400 below ground
Pipe laid and backfilled |
|
08-FEB-2023 |
Andrew Dawson |
Poles and struts for 3 wells
Connected 3 wells
Started last trench |
|
07-FEB-2023 |
Andrew Dawson |
Repaired 315mm header line
Connected 2 wells
|
|
06-FEB-2023 |
Andrew Dawson |
Cleaned up trench from previous day
Trenched and backfilled flowline |
|
03-FEB-2023 |
Andrew Dawson |
Finished trench to E station
Welded risers beside wells along the line
|
|
02-FEB-2023 |
Andrew Dawson |
Trenched 80m x 110 line
Note: Portion of trenched required bench due to depth. |
|
01-FEB-2023 |
Andrew Dawson |
Landed in Sydney
Picked up ute from DMS, and picked up tools and generator from Elizabeth drive.
Arrived at site midday
Continued trenching towards E station
|
|
31-JAN-2023 |
Andrew Dawson |
No one on site - Shift Change No Works
Log created to capture hire equipment
|
|
30-JAN-2023 |
Andrew Dawson |
No one on site - Shift Change No Works
Log created to capture hire equipment
|
|
27-JAN-2023 |
Andrew Dawson |
No one on site - Shift Change No Works
Log created to capture hire equipment
|
|
26-JAN-2023 |
Andrew Dawson |
No one on site - Shift Change No Works
Log created to capture hire equipment
Public holiday |
|
25-JAN-2023 |
Andrew Dawson |
No one on site - Shift Change No Works
Log created to capture hire equipment
|
|
24-JAN-2023 |
Andrew Dawson |
Clean up site for management meeting
Backfill holes at D12 - Sump 8 |
|
23-JAN-2023 |
Andrew Dawson |
Finish well D28
Backfill holes at D12 - Sump 8 |
|
22-JAN-2023 |
Andrew Dawson |
No work on site today - Site log just for Marie |
|
21-JAN-2023 |
Andrew Dawson |
Trenching lateral header from well D12 back towards E station |
|
20-JAN-2023 |
Andrew Dawson |
Backfill well D28
Start lateral header from well D12 back towards E station |
|
19-JAN-2023 |
Andrew Dawson |
Finish j trap on flow line to well D28
Rained off at 10.30am |
|
18-JAN-2023 |
Andrew Dawson |
Day Works
Run flow line to well D28 and install J trap |
|
17-JAN-2023 |
Andrew Dawson |
Fit 2 seal cap x 2 hour
Install flow line to well D18 |
|
16-JAN-2023 |
Andrew Dawson |
Fit seal cap x 1 hour
Finish well heads
Help Jonesy find O2 Leak x 2 hours
Start flow line to well D18 |
|
15-JAN-2023 |
Andrew Dawson |
Trench flow lines to wells off D riser pipe - K110 - K111 - K112 completed |
|
14-JAN-2023 |
Andrew Dawson |
Trench flow lines to wells off D riser pipe - K110 - K111 - K112 |
|
13-JAN-2023 |
Andrew Dawson |
Trench flow lines to wells off D riser pipe - K110 - K111 - K112 |
|
12-JAN-2023 |
Andrew Dawson |
Excavate around new wells and seal better with bentonite - K105 - K108 - K109 |
|
11-JAN-2023 |
Andrew Dawson |
Excavate around new wells and seal better with bentonite - K102 -K103 |
|
10-JAN-2023 |
Andrew Dawson |
Fit pump back in KOP 4 |
|
09-JAN-2023 |
Andrew Dawson |
Fit pump back in KOP 4 |
|
22-DEC-2022 |
Andrew Dawson |
Finish end caps on 8 wells |
|
21-DEC-2022 |
Andrew Dawson |
Trenching flow lines
Finish LP04 head works
|
|
20-DEC-2022 |
Andrew Dawson |
Trenching flow lines
Finish LP04 head works
As per Russ/Andrew.....
Dump truck was off hired at the COB ??
Russell is taking laser back to Kennards tomorrow. |
|
19-DEC-2022 |
Andrew Dawson |
Trenching flow lines
Gas line shut down |
|
18-DEC-2022 |
Andrew Dawson |
Trenching flow lines |
|
17-DEC-2022 |
Andrew Dawson |
Trenching flow lines |
|
16-DEC-2022 |
Andrew Dawson |
Trenching flow lines |
|
15-DEC-2022 |
Andrew Dawson |
Trenching flow lines Teeing into ring main while Austral are offline |
|
14-DEC-2022 |
Andrew Dawson |
Trenching flow lines |
|
13-DEC-2022 |
Andrew Dawson |
Trenching flow lines |
|
12-DEC-2022 |
Andrew Dawson |
Get set up on site - had to wait for excavator - Start trenching flow lines |