06-MAY-2023
Richard Andrews
13125 Gipps Street Landfill Gas Barrier Blanket Gipps Street Reserve
Pick up 1t excavator from Coates and drive it out to site.
Pre start with all contractors. Unload 1t machine and pre start.
Get machines inducted by Scott.
Using 1t excavator on western end, use spoil from previous anchor trench to build out dirt so excavator can fit beside piles.
Wasn't quite enough dirt so track 8t excavator around the other side and throw some dirt down to 1t.
If i was to start this trench i have nowhere to put the spoil apart from where Scott needs to put his drain.
I called Scott up there to see if he wanted to  install his drain first and that way we can put the spoil on top and then remove when back filling. He agreed this would be better.
We then moved onto the Northern side. Cleaned up and levelled off ground while tracking down the end.
Started trenching, ground was very hard and was very slow digging. Small teeth on bucket and big gap between teeth made it difficult.
Continue Northern trench.
Installation
 
Log - Site Name
Daily Log Date
Item
Size (mm)
Quantity/Length
(no. or m)
 
Gipps Street Reserve 06-MAY-2023 Trenching (Excl. Pipe)   10
TOT         10
Milestones
Anchor Trench - 160m x 500W x 400D Yes  
Horizontal Well - 350m x 90mm Yes  
Flow Line - 135m x 90mm Yes  
Vent Stack - 2 off Yes  
Scope 2: A84 Bidim - 1,460m2 x 1 layer & 1,200m2 x 2 layers  
HDPE Liner - 1,200m2 x 1 layer Yes  
Screw Pile Boots - 40 off Yes  
Flow line Boots - 2 off Yes  
Variation No.11353 - Interruption to Project Yes  
Variation No.11362 - Greentech Consultancy  
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.