12116
MRL - Landfill Gas Collection System Modification - Header Line and Manifold
Cleanaway Waste Management Ltd
Melbourne Regional Landfill
1100-1152 Christies Rd, Ravenhall, Victoria 3023 Australia

Complete
 
Date
Document Type
Document
 
Issued for Construction Drawing Set  (2 Document records) 
15-JUL-2020 Issued for Construction Drawing Set Doc
10-JUL-2020 Issued for Construction Drawing Set Doc
Landfill Gas Collection System Modification

Run Energy will:

  • Modify main header line
  • Install lateral header line
  • Modify well station manifolds
  • Modify in accordance with attached design drawings:
    • MRL-GCS-001 

Details:

Item Quantity/Size Installation Notes
Main header line 450 mm x 125 mm reducing tee
  • Connect in 450 mm main header line with a reducing tee to 125 mm
  • Refer to the attached design drawing
Lateral header line 80 m x 125 mm PN8
  • Weld and lay  on the landfill cap
  • Refer to the attached design drawing for the pipe route 
Well station manifold 2
  • Connect proposed lateral header line to well station 3A & 2C
  • Refer to the attached design drawing for the locations
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1 Main header line connect 450mm x 125mm tee Day 1   Yes  
2 Weld & lay Lateral header line 80m x 125mm Day 1   Yes  
3 Connect 3A & 2C Well station manifold Day 2   Yes  
4 GPS & clean up (Payment: $12,413) Day 2 Yes    
5    
6    
7    
8    
9    
10    
 
Date Issued
Equipment Type
Equipment Serial ID
 
12116  (19 Record records) 
22-JUL-2020 EF Welder 180602575
22-JUL-2020 Laser Level 255431
22-JUL-2020   GCBCT-2085011
21-JUL-2020 EF Welder 180602575
21-JUL-2020   GCBCT-2085011
21-JUL-2020 Laser Level 255431
21-JUL-2020 Personal Gas Monitor KA416-1073217
20-JUL-2020   GCBCT-2085011
20-JUL-2020 EF Welder 180602575
20-JUL-2020   GCBCT-2085011
20-JUL-2020 EF Welder 180602575
20-JUL-2020 Personal Gas Monitor KA416-1073217
20-JUL-2020 Laser Level 255431
17-JUL-2020   GCBCT-2085011
17-JUL-2020 EF Welder 180602575
17-JUL-2020 Personal Gas Monitor KA416-1073217
16-JUL-2020   GCBCT-2085011
16-JUL-2020 EF Welder 180602575
16-JUL-2020 Personal Gas Monitor KA416-1073217
 
Date
Team Lead
Work Summary
 
12116 - MRL - Landfill Gas Collection System Modification - Header Line and Manifold  (7 Daily Log records) 
29-JUL-2020 Nicholas Barned Pick up GPS from Clayton office and travel to MRL
Unable to GPS as unit not working - only picking up 4 satellites and no real time corrections
Troubleshoot with Reg - organise unit to be dropped off back at office tomorrow
22-JUL-2020 Nicholas Barned Backfill pipe around station
Place material underneath hanging areas on pipe
Place material over pipe once in final position
Clean up area and remove scrap pipe back down to yard
21-JUL-2020 Nicholas Barned Prepare pipe near station for tie in
Prepare 450mm pipe for tie in
Isolate field
Tie in 125mm line into station and 450mm line 
20-JUL-2020 Nicholas Barned Variation #1 
Repair 90mm flowline - cut and replace pipe and weld sockets

20-JUL-2020 Nicholas Barned Trim pad to height for 125mm header line to sit on
Excavate around Well station on header line to allow for tie in and capping of existing pipe
Drag pipe up to works area and lay in position and check fall
17-JUL-2020 Nicholas Barned Buttweld 125mm pipe for new header line
Build ramp for header line to sit on from station tie in point to 450mm line tie in point
16-JUL-2020 Nicholas Barned Go over work scope with Tom M.
Organise excavator to be delivered
Travel to Clayton factory to pick up Butt welder, laser and fittings
Expose header line tie in point at well station by hand
Work out heights and required fall needed for header line and where we can tie in to
Clean out containers and sort out fittings while waiting for excavator
Weld reducers onto 450-315 tee ready for install
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
11-FEB-2021 Melbourne Regional Landfill Job GCS As-Built MRL - H Station Header 12116 12116 Dwg
No
No
No
No
Russell Clarke
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.