12549
Erskine Park Landfill GCS Modification
Cleanaway Waste Management Ltd
Erskine Park Landfill
85-87 Quarry Rd, Erskine Park, New South Wales 2759 Australia

Complete
Landfill Gas Collection System Modification

Run Energy will:

  • Modify main header line
  • Modify optic fibre  

Details:

Item Quantity/Size Installation Notes
Main header line 50 m x 315 mm PN10
  • Excavate and remove the following:
    • 50 m x 315 mm header line
    • 50 m x 110 mm leachate return line 
    • 50 m x 63 mm air line
    • 50 m x 63 mm conduit 
  • Excavation to be left open for installation of pipe
  • Install by-pass line on surface  
    • 90 m x 315 mm header line using 50m of removed pipe plus pipe on site (3 x 20 m x 315 mm PN10 still on site)
    • 100 m x 63 mm fibre conduit between 2 of the inspection pits
Optic fibre 100 m x 12 core optic fibre
  • Remove the following:
    • 50 m of optic fibre 
  • Install by-pass line 
    • 170 m of optic fibre between 2 of the inspection pits
Main header line  50  m x 315 mm PN10
  • Reinstall the following:
    • 50 m x 315 mm header line
    • 50 m x 110 mm leachate return line 
    • 50 m x 63 mm air line
    • 50 m x 63 mm conduit 
  • Allowance for 3 compaction tests only
Optic fibre 100 m  x 12 core fibre optic
  • Reinstall existing pipe line route 
    • 100 m of optic fibre between 2 of the inspection pits
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1 Main Header Line - 50m x 315mm  excavate & remove   Yes  
2 Optic Fibre - 100m x 12 core remove   Yes  
3 Main Header Line  - 50m x 315mm Reinstate   Yes  
4 Optic Fibre - 100m x 12 core, reinstate   Yes  
5   Yes  
6   Yes  
7   Yes  
8   Yes  
9   Yes  
10   Yes  
 
Date Issued
Equipment Type
Equipment Serial ID
 
No Record records found
 
Date
Team Lead
Work Summary
 
12549 - Erskine Park Landfill GCS Modification  (15 Daily Log records) 
27-APR-2022   Dig out and instal last big pit.
06-APR-2022   Pick up pits and crow bar from Sydney office.
Investigate gas leak in main header line. ( could smell a slight gas scent around the riser off austral header from where the Blatter was in but couldn't dig right down to header to continue to investigate).
Dug out old communications pit and placed in new one.
03-FEB-2022   Clean off all mud from work area.
Sand trench, place trench tape then 200mm layer of clay. Compact layers up until 500mm.
Uncoil 63mm conduit, install in trench, trench tape and continue compaction process till reached top.
Squeeze off and install hard caps on both risers off the saddles.

Repaired 90mm flow line.
Both screw caps where used on the air and leachate that are unused pipe at the austral KOP.
02-FEB-2022   Due to wall builders blocking drain, caused run off from the landfill to enter trench line.
Dewater for most the morning & avoid anymore run off to enter trench.
Clean out some dirt from trench & clean mud from area.
Remove isolation points from header, install reducers, riser with cap.
Pressure test header.
Uncoil 110mm pipe and install.
01-FEB-2022   Walk through with Daniel ( Cleanaway) on days works
Picked up fittings from Sydney office (Ben), Picked up generator and necessary equipment for tasks ( Pops).
Bring equipment down to work area.
Expose either end of the header line, saddle and isolate both ends of works, cut one side of the elbows.
Expose and remove header from work area.
Dig & sand trench.
Lay 355mm header, add short piece of pipe to make up full length. 
Set up area for rain to divert into drain.

Ben listed the Asset numbers on the daily log for Erskine Park dated 3rd Feb.
admin has updated the asset numbers according to the log.
03-DEC-2021 Richard Andrews Pick up parts from kenkar.
Grab pipe from pipe rack and take down to work area.
Scrape 400mm sump.
Weld 2 pieces of 225mm pipe together to get 3m, clamp 63mm flow line and cut off well head. Weld well head onto 225mm pipe. Weld 3m of 63mm on to flow line. Raise well 3m.
Cut off 400mm well head and weld onto 400mm pipe. Raise sump 3m.
Expose and clamp sump flow line, raise 4m.
Cut and cap J trap.
Take left over pipe up to pipe rack. 
29-NOV-2021 Richard Andrews Pick up fittings from Jonesy's.
Go to bunnings and get some gear for job.
Arrive on site and check out pipe and work to be done.
Cut and scrape 400mm pipe, load pipe onto ute.
Request machine to bring down 400mm pipe.
Scrape, cut and remove head from sump 10, weld head onto new pipe. Inspect head for leaks and fill with sikaflex.
Clamp cut and remove flow line, weld valve on flow line extension.
Expose around J trap and cut down and end cap.
Prepare air, leachate and barra trap risers.
Raise well 10 4m and hold in position for weld and cool time. (1h 35m)
Raise flow line 4m and tape to sump as far as we can reach with no machine.
Clamp and cut air and leachate, cut barra trap riser, weld caps onto extensions.
Raise air, leachate and barra trap 3m. Brace with star picket and rope as we have no excavator.
Pack up and take left over pipe and well head up to pipe rack.

To wet to access next work area.
07-OCT-2021   Meet Geoff from austral, help get them back online with Dave Tracey.
Clean up rubbish remove with dump truck before it was picked up.
Backfill both ends of header.
Tidy up work area.
06-OCT-2021   Expose Eastern end, open area.
Trench 8m so pipe has cover over it.
Trench in conduit further down so it can sweep around.
Cut austral header placed in shut off balloon.
installed all elbows.
05-OCT-2021   Expose around 355 header line, cut conduit, air and leachate out of the way. 
Trench out 15m and continue to trench along an extra  25m and run out ground at toe of batter.
installed pipe, will backfill once tied in.
Pick up fittings.
04-OCT-2021   Public holiday.
03-OCT-2021   No works.
02-OCT-2021   Pipe wrong size to fittings.
Drag around 70m piece of pipe to the work zone.
Take all fittings to fitting container at Elizabeth dr.
Austral back online until works can resume on Tuesday.
01-OCT-2021   Pre start.
Talks with Daniel and wall builders about location of pipe. ( no decision made till later in the day about how close machine can go to subsidence. End result, not removing pipe from ground in that area. From center of subsidence 15m each side is where the elbow will go. Can excavate 1m towards subsidence and only excavate back away from it.
Roll out coil, Clear track for conduit to sit on.
Excavate around optic pit as pits completely caved in.
Pick up fittings from Kenkar.
Source out 315mm pipe, cut out tears in pipe and make up 15m.

 
30-SEP-2021   Inductions for labor hire guys.
Site walk around run through of work area.
Unload 63mm conduit.
Leave xxk117 onsite, drop Justin back at Elizabeth dr.
Bunnings to get tape for isolation balloon and other items.
( Machines added to log, daily charge is at Elizabeth dr so ticked no charge for this job).
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
09-SEP-2022 Erskine Park Landfill Job GCS As-Built As built 12549 12549 Dwg
No
No
No
No
Russell Clarke
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.