Leachate Collection System Installation

Run Energy will:

  • Install leachate sump headworks
  • Trench, weld and lay leachate line
  • Weld and lay air line
  • Install air and leachate risers
  • Install in accordance with attached design drawing:
    • Melbourne Regional Landfill - Leachate System Installation - Dwg 015-DN-025

Details:

Item Quantity/Size Installation Notes General Arrangement Drawing Reference
Leachate line 1,760 m x 200 mm PN10  Weld and lay on ground surface as per design drawing N/A
Road crossing 12 m x 450 mm PN10 Trench weld and lay road crossing. Use class 2 road base for backfill and compact as required. RE-LFG- 187 - Road Crossing
Air line 1,850 mm x 63 mm PN16 Weld and lay on ground surface as per design drawing N/A
Air and leachate risers 7 x 63 mm PN16 Complete valve train and frame RE-LFG-143 - Air & Leachte Riser Manifold
  • No variations
Pump Supply

Run Energy will supply:

Item Quantity/Unit
Airwell BF8009A (200m x 0.9m) sump pump on skids 3
Solar controller 3
Cable kit 3 x 75 m
Seal cap 3 x 540 mm ID
Air regulator/cycle counter 3
Exhaust pipe/support pole  3
Air pump kit 3
Liquid level tube arrangement 3
  • No variations
Pump Installation

Run Energy will:

  • Assemble pumps offsite
  • Install pumps
  • Install liquid level tube arrangements
  • Install stainless steel and communication supporting cables
  • Install control box complete with air regulator and cycle counter
  • Install lids and seal caps
  • Install exhaust/support poles
  • Connect to leachate collection system
  • Commission pumps

Details:

Item Quantity/Details
Pump 3 x Airwell BF8009A (200m x 0.9m) sump pump on skids
Connection to leachate collection system Air and leachate risers at each location
  • No variations
No. Description Scheduled Billing Milestone Complete Complete is checked in the LFG Construction Daily Log
1 Additional Works (variation)   Yes  
2   Yes  
3   Yes  
4   Yes  
5    
6   Yes  
7   Yes  
8   Yes  
9   Yes  
10    
 
Date Issued
Equipment Type
Equipment Serial ID
 
No Record records found
 
Date
Team Lead
Work Summary
 
14022 - MRL Leachate Collection System - Additional Works  (16 Daily Log records) 
16-NOV-2023 Reg Blair 14022 leachate

Remove sqeeze offs from 160mm isolations
Reset squeeze offs on 200mm leachate line to install 200mm isolation valve between North and South leachate systems
Track excavator back to northern side
pops 3
Tom 3
Marto 3
15-NOV-2023 Reg Blair 14022 leachate

Expose 160mm leachate line going up access ramp to southern expansion area cell 1, relocate leachate line outside of cell 2 construction area. Isolate and cut for realignment.

Excavator 8hrs
11-NOV-2023 Reg Blair 14022 leachate

no works
10-NOV-2023 Reg Blair 14022 leachate

rewalk line as line was not holding pressure, fix leaks
keep presure testing.

10-NOV-2023 Andrew  Dawson Pressure Test Lines
09-NOV-2023 Reg Blair 14022 leachate

Installed Flanges and gaskets to flow meter, welded.
Installed tee piece to commission line. walked entire line.
Welded 2m of 110 onto 110 near flow meter with end cap.
Tested line. Valves were leaking. Tightened up bolts required and walked line again.
Re tested and left to sit with pressure overnight.
08-NOV-2023 Reg Blair Uncoiled 1x 63mm 100mm coil
Moved into place
scouted site for more 63 as we were short.
Found some shorter lengths on other side.
Dragged over and welded all lengths to get to the flow meter.
removed scrap 200mm pipe from work area and tidied up

Note-
marie/keysie 
ive made a mess of the time sheets across 3 different logs, which are correct but might look like a bit of a mess.(andrew)
In short:
Craig Weir
Pops
Johnny
tommy 
all 9 hours to site.
03-NOV-2023 Reg Blair No Variation no.
Day Works

buttweld flange onto 2m piece.
Packup butt welder.
Bring final pieces of pipe required into compound, weld all together.
Get flow meter in place, missing flanges to complete.
Bolt control valve on near entrance of compound.
02-NOV-2023 Reg Blair No Variation No.
Reference 'Day Works:


Butt welded remainer of 200mm pipe.
Dragged 120m into leachate pond compound and roughly put in place.
Butt welded tees and flanges to lengths of pipe.
Cut out flow meter and moved to new position, replaced with plain pipe to get back into compoound. welded


Down time with butt welder due to cutter plate issue. Was sorted.


Excavator 9 hours
01-NOV-2023 Reg Blair No Variation No.
Reference 'Day Works:


Butt welded all day.
Down time with butt welder due to cutter plate issue. Was sorted.


Excavator 9 hours
31-OCT-2023 Reg Blair No Variation No.
Reference 'Day Works:


Finalized all welds on 200mm leachate line and 63mm airline
Dragged 30mm of 200mm pipe through to leachate pond and connected.
Pinned header  in several locations.
Started butt welding 200mm pipe


Excavator 9 hours
30-OCT-2023 Reg Blair No Variation No.
Reference  'Day Works'


Recieve delivery of 200mm pipe and 63mm coils

Install 2 x 200mm isolation valves, 1 x 110mm future tee, 1 x 90mm tee pump out or in pressure test line
lay and weld 100m length of 200mm pipe
lay 100m of 63mm airline
pull out 2x 100mm 63 coils

Excavator 8 hours
28-OCT-2023 Reg Blair No Variation No.
Reference 'Day Works'

ed 200mm leachate & 63mm air pipe thru sleeve and dropped into 1.5m trench for road crossing
Johnny 4hrs
Craig weir 4hrs

Materials used 
100m of 200mm pipe
100m of 63mm pipe
1x roll duct tape

Excavator 4hrs

27-OCT-2023 Reg Blair No Variation No.
Reference 'Day Works'


Buttwelding 200mm pipe for leachate line

Excavator 8 hours
26-OCT-2023 Reg Blair No Variation No.
Reference "Day Works"

Buttwelding 200mm

Repair 63mm air line near kop18 hit by delta

John 10
Craig 10
Nic 10

Excavator 8 , raining onsite

Materials
1 x 63mm e/f socket
25-OCT-2023 Reg Blair Buttweld 4 x 200mm stub flanges and assemble isolation valves
Transport pipe from power station to the rear of site for butt welding, moved by membreys transport

John 10
Craig 9

Excavator not used, raining onsite
Yes
 
Date
Site Name
Type
Title
Run Job Number
CQA Report
Job Number
Drawing
 
15-MAR-2024 Melbourne Regional Landfill Job GCS As-Built As built 14022 14022 Dwg
No
Yes
No
The search criteria for this report references restricted fields.
Yes
Unable to display report. You do not have sufficient permission.
Russell Clarke
Dean Wilson
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.