27-FEB-2021 |
Richard Andrews |
Repair LS02.
Note: Lunchroom is still on hire until the next project |
|
26-FEB-2021 |
Richard Andrews |
Travel to Melbourne. |
|
23-FEB-2021 |
Richard Andrews |
No work on site |
|
22-FEB-2021 |
Richard Andrews |
Clean up excavator
General clean up office |
|
19-FEB-2021 |
Richard Andrews |
Clean up around concrete anchors so have walkway above water level to access KOP
General clean up of pipe |
|
18-FEB-2021 |
Richard Andrews |
Clean up around concrete anchors
General clean up of pipe |
|
17-FEB-2021 |
Richard Andrews |
Walk through site with Kate.
Install stickers on risers.
Install yellow men on 2 wells.
General clean up of site.
|
|
16-FEB-2021 |
Richard Andrews |
Install pump in KOP.
Weld and lay 10m of 63mm air and 10m of 63mm leachate line.
Finish off form work and pour concrete.
Start installing stickers on risers. |
|
15-FEB-2021 |
Richard Andrews |
Continue form work for concrete slabs in hanson land.
Make and install 450mm pits to protect valves.
Start putting together valves for pump. |
|
12-FEB-2021 |
Richard Andrews |
Prep ground around KOP for concrete slab.
Box up form work around KOP.
Weld and lay 75m of 160mm and 75m of 125mm header.
Install 315mm tee and 160mm valve.
Clean and off hire 14t excavator. |
|
11-FEB-2021 |
Richard Andrews |
Install poles and struts on 4b.
Work out and purchase form work for concrete slabs. |
|
10-FEB-2021 |
Richard Andrews |
Install isolation valves on air and leachate risers and connect pump.
Tie in air and leachate.
Clean up around LS01.
Re install flow lines and connect wells requested by Kate.
Continue works on wells in stage 1. |
|
09-FEB-2021 |
Richard Andrews |
Fill out JSA for sump raise, go to boral and fill out permits.
Transport concrete collar to work area.
Remove lid from LS01 and extend 90mm pipe going into sump.
Raise concrete sump 2.6m and reinstall lid.
Make pump and install in sump to 8.6m
Make bund around KOP in hanson land.
Drag pipes up to well station 3b.
Pin 160mm header. |
|
08-FEB-2021 |
Richard Andrews |
Weld and lay 132m 160mm lateral header line.
Back fill either side of road crossing.
Raise well 4m.
Weld and lay 60m of 110mm flow line.
Install metre run on 1 well and connect to flow line.
Run loads of fill to boral.
Organise fittings for well station 3B.
Off hire dump truck. |
|
06-FEB-2021 |
Richard Andrews |
Butt welding. |
|
05-FEB-2021 |
Richard Andrews |
20t excavator serviced.
Go to boral, sign in and sort out permits.
Install leachate riser and back fill and clean up around sump.
Build bund around KOP in hanson land.
Receive and unload concrete pipes for sump raise.
Finish off pump work for Jude.
Trench and install 450mm sleeve for road crossing. |
|
04-FEB-2021 |
Richard Andrews |
Go to boral sign in and sort out permits.
Weld and lay 30m of air and leachate line to sumps.
Finish sanding up trench.
Cart in dirt to put over sand to protect from rocky back fill material.
Back fill and clean up.
Install air riser with sleeve.
Continue work on pumps.
Raise and reinstall well station 4b.
Receive excavator.
Return bollards and signs. |
|
03-FEB-2021 |
Richard Andrews |
Go to boral, sign in and get permits sorted.
Load up coils and take to boral, pull out coils.
Weld and lay 100m of 63mm and 90mm.
Feed pipes through sleeve and back fill around road, rebuild bunds on edge of road.
Continue setting pumps 250mm off bottom of sumps. |
|
02-FEB-2021 |
Richard Andrews |
Go to boral and sign in and sort out permits.
Hayden compete boral induction.
Trench from road crossing to sump. Hard going very rocky.
Lowering pumps for Jude.
Return compaction plate. |
|
01-FEB-2021 |
Richard Andrews |
Go to boral and sort out permits and sign in.
Trench weld and lay 24m of 280mm sleeve across haul rd.
Back fill, compact and clean up.
Remove pump from Sump 17 and install screw cap to seal odour.
Smooth out ground for 160mm header to lay on.
Clean up containers.
Pick up compaction plate. |
|
29-JAN-2021 |
Richard Andrews |
Load up vehicles and look at road crossing, unable to do due to weather.
Complete boral inductions.
Rained off. |
|
28-JAN-2021 |
Richard Andrews |
Finish butt welding 160mm header.
Investigate missing well, found well and exposed. Well had been cut by machinery and was full of dirt, exposed and cut a further 2m down and still full of dirt. Backfilled.
Sort out leachate issues.
Make a start on well station 4b.
Install 2 x 90mm valves on leachate line.
Pick up bollards and road signage from Kennards, didn't have time to pick up wacker. |
|
27-JAN-2021 |
Richard Andrews |
Connect barra trap to header running to 2 wells, fill trap with water and back fill and clean up.
Isolate V station and tie in 2 new wells.
Butt welding 160mm header.
Clean up leachate spill and make repairs. |
|
26-JAN-2021 |
Richard Andrews |
Public holiday. |
|
25-JAN-2021 |
Richard Andrews |
No works.
No daily charge box ticked for Onetrak equipment 2 x excavators & 1 x dump truck....
RE: RE: Hire equipment - Question
From: philcoghill@runenergy.com
Sent: Fri, 29 Jan, 2021 at 10:39 am
To: adminaus@runenergy.com
Yes I did stand down before the long weekend – spoke to Rhodes on the Friday
Regards, Phil Coghill
|
|
22-JAN-2021 |
Richard Andrews |
Flag off header line and open hole.
Vacuum testing. |
|
21-JAN-2021 |
Richard Andrews |
Relocate tool containers down to power station. Tidy up container.
Put together valves and install 5 x 2 inch valves on air lines.
Finish pinning header line with fill.
Install well head on 225mm well and connect, install test head on header for vac test.
Smooth out ramp to well X163, weld and lay 25m of 110mm flow line and connect to well.
Investigate valve to isolate header line for tie in, unable to locate.
Expose header line upside of valve to check for damage, will tie in here.
Investigate missing well..
|
|
20-JAN-2021 |
Richard Andrews |
Pipe anchors installed. |
|
19-JAN-2021 |
Richard Andrews |
Work out pipe and fittings for connection on 225 wells.
Tie in leachate to last KOP and turn on.
Clean up scrap pipe.
Trench weld and lay 100m of 225mm header.
Back fill.
Make up barra trap.
Install 250mm cap on redundant header line. |
|
18-JAN-2021 |
Richard Andrews |
Relocate air and leachate up next to new header, tie in sump and KOP's.
Tie in 450mm tee and 250mm tee. |
|
15-JAN-2021 |
Richard Andrews |
Tie in leachate to KOP on batter in hanson land.
Flag off buried header.
Continue pinning header line.
Clean up scrap pipe.
GPS barra traps and 90mm valves. |
|
14-JAN-2021 |
Russell Clarke |
Install flagging from 1st KOP to tie in point.
Tie in leachate at KOP near shamrock.
Josh onsite, pressure test air and leachate near power station and inspect flagging and yellow men on wells.
Tie in air and leachate near power station.
Start pinning header line.
Start cleaning up scrap pipe. |
|
13-JAN-2021 |
Russell Clarke |
String bunting along header line.
Extrusion weld divots in header line.
Get set up for pressure test on air and leachate. |
|
12-JAN-2021 |
Russell Clarke |
String bunting along header line |
|
11-JAN-2021 |
Russell Clarke |
String bunting along header line |
|
08-JAN-2021 |
Richard Andrews |
|
|
07-JAN-2021 |
Richard Andrews |
|
|
06-JAN-2021 |
Richard Andrews |
|
|
05-JAN-2021 |
Richard Andrews |
|
|
04-JAN-2021 |
Richard Andrews |
|
|
01-JAN-2021 |
Richard Andrews |
|
|
31-DEC-2020 |
Richard Andrews |
|
|
30-DEC-2020 |
Richard Andrews |
|
|
29-DEC-2020 |
Richard Andrews |
|
|
28-DEC-2020 |
Richard Andrews |
|
|
24-DEC-2020 |
Richard Andrews |
No works but left on site over christmas break 3 containers 24th of December to the 10th of January
1 office - Royal Wolf
1 smoko room - Royal Wolf
1 storage - Coates |
|
23-DEC-2020 |
Russell Clarke |
Tie in leachate to KOP near haul rd.
Weld screw caps on J traps.
20t excavator on stand down till 11 Jan. |
|
22-DEC-2020 |
Russell Clarke |
Relocate air and leachate up on bench with our new header line and tie in to new lines. Cap old lines.
Connect J trap to flow line.
Tie in leachate to KOP near back tie in point.
Stand down 14t excavator till 11 Jan.
Heavy rain, wet and muddy conditions. |
|
21-DEC-2020 |
Russell Clarke |
Backfill holes around barra traps.
Install yellow man cut outs and reflective tape on wells.
Tie in and cap air and leachate at 3 locations.
Repair leachate line at LP21. |
|
20-DEC-2020 |
Russell Clarke |
No works. |