26-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment
Purchasing has request off hire of lunch room - waiting on Coates to advise collection date
Lunch room was picked up around lunch time |
|
25-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment
Purchasing has request off hire of lunch room - waiting on Coates to advise collection date |
|
24-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
23-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
22-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
21-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
20-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
19-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
18-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
17-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
16-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
15-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
14-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment
Excavator was off hired at COB
|
|
13-JUN-2024 |
Richard Andrews |
No works completed on this job
Log created to capture hire equipment |
|
11-JUN-2024 |
Richard Andrews |
No works on this job
Log created to capture hire equipment |
|
10-JUN-2024 |
Richard Andrews |
No one on site
Public holiday |
|
07-JUN-2024 |
Richard Andrews |
Log created to capture hire equipment
|
|
06-JUN-2024 |
Richard Andrews |
Log created to capture hire equipment
|
|
07-MAY-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
06-MAY-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
03-MAY-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
02-MAY-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
29-APR-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
28-APR-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
25-APR-2024 |
Richard Andrews |
Log created to capture hire equipment that was raised under job No.14009
Used on another job but Dean happy to capture and leave under Job no.14009 |
|
19-MAR-2024 |
Richard Andrews |
Deconstruct drill pads and clean up batter. |
|
18-MAR-2024 |
Richard Andrews |
Clean up drilling waste from wells on batter.
Start deconstructing drill pads. |
|
16-MAR-2024 |
Richard Andrews |
Drill and complete well W6-4 to 26.2m. Drilling finished.
Get set up for road crossing.
Trench and lay 24m of 450mm sleeve across road.
Back fill and compact.
Fire on the tip face, assist cleanaway and make track around trench for fire trucks. Direct traffic.
Night works. Start 12pm Sat finish 1am Sun. |
|
15-MAR-2024 |
Richard Andrews |
Drill and complete well W4-1 to 11.7m.
Finish off pad for W6-2.
Drill and complete well W6-2 to 11m.
Build pad for W6-4.
Organise gear for road crossing.
|
|
14-MAR-2024 |
Richard Andrews |
Drill and complete well W4-4 to 9.6m.
Drill and complete well W4-3 to 10.5m.
Drill and complete well W4-2 to 10.8m.
Build pad for W4-1, start pad for W6-1. |
|
13-MAR-2024 |
Richard Andrews |
Building drill pads on batter.
Driller day off. |
|
12-MAR-2024 |
Richard Andrews |
Drill and complete W3-1 to 9m.
Drill and complete W4-6 to 10m.
Drill and complete W4-5 to 11.3m.
Build pad for W4-4. |
|
11-MAR-2024 |
Richard Andrews |
Drill and complete well W3-2 to 11m.
Drill and complete well W3-4 to 8.2m.
Build pad for W3-3.
Drill and complete well W3-3 to 12m.
Build pads for W3-1 and W4-6.
Catch up on drill logs. |
|
10-MAR-2024 |
Richard Andrews |
Touch up pad for well 19.
Drill and complete well W3-19 to 13.6m.
Build pad for well 24.
Drill and complete well W3-24 to 13m.
Finish off pad for well W3-2 and set up drill rig.
Build pad for W3-4. |
|
09-MAR-2024 |
Richard Andrews |
Drill and complete well W3-7 to 20m.
Drill and complete well W3-8 to 13m.
Drill and complete well W3-13 to 13.3m.
Build pad for W3-19. |
|
08-MAR-2024 |
Richard Andrews |
Drill and complete well W3-5 to 26.4m.
Drill and complete well W3-6 to 25m.
Weld and lay 100m of 160mm header line.
Isolate and tie in new header line.
Wells W4-29, W4-28, W4-22, W4-23, W4-16, W4-17, W4-18 are now online.
Receive and stockpile loads of fill for drill pads. |
|
07-MAR-2024 |
Richard Andrews |
Drill and complete well W4-7 to 30m.
Set up on W4-12, drill and complete to 27.4m
Butt weld last 6 wells.
Receive and heap loads of fill for drill pads. |
|
06-MAR-2024 |
Richard Andrews |
Set up on W3-23, drill and complete to 20.1m.
Track rig over to Northern side of haul road.
Run through plan with driller, look at wells on batter.
Set up on W6-5, drill and complete to 29.5m.
Set up on W4-7.
Excavator M388 serviced, down for 2 hours. |
|
05-MAR-2024 |
Richard Andrews |
Drill W3-10 to 28.8m and complete
Drill and complete W3-18 to 23m.
Build test pad on batter.
Touch up pad for W3-23.
Check what stringers still need to be made and check perf stocks. |
|
04-MAR-2024 |
Richard Andrews |
Assist driller installing new rope and changing back to short bar.
Work on drill pads.
Set back up on W3-12, drill from 23 to 26m. Install and complete well.
Set up on W3-10. |
|
03-MAR-2024 |
Richard Andrews |
Set up on W3-12, drill to 23m then rope frayed. Drilling stopped 11am.
Continue connecting flow lines to wells and station.
Build pads for wells W3-18 and 23.
Assist with removal of rope and bar.
Lot of rubbish stuck in bar. |
|
02-MAR-2024 |
Richard Andrews |
Drill and complete well W3-17 to 27.4m.
Drill and complete well W3-11 to 28.3m.
Weld and lay 140m of 90mm flow line to wells W4-28, 22 and 16.
Continue connecting flow lines. |
|
01-MAR-2024 |
Richard Andrews |
Pulled out a heap of 90mm coils.
Weld and lay 250m of 90mm flow line to wells W4-29, 23, 17 and 18.
Start connecting flow lines.
Install end caps on wells.
Driller sick again. |
|
29-FEB-2024 |
Richard Andrews |
Weld and lay 70m of 250mm header line.
Tie in new header line running into Phase 4.
6 new wells now online.
Install 2nd well station in Phase 4. 2 x manifolds.
Install end caps on wells.
General clean up of Phase 4 wells.
Driller sick. |
|
28-FEB-2024 |
Richard Andrews |
Drill and complete well W3-16 to 29.3m.
Drill and complete well W3-22 to 29.3m.
General clean up around containers.
Weld and lay 310m of 90mm flow line to wells W4-26, 19, 20, 14 and 15.
Connect flow lines to wells and well stations.
Build next well station pad in Phase 4. |
|
27-FEB-2024 |
Richard Andrews |
Continue drilling W3-15 from 5 to 30.6m. Complete well.
Set up on W3-21, drill and complete to 30m.
Try and clean out stuff stuck in kelly bar.
Clean up around wells.
Back fill road crossing.
Pull out coils and bring over to work area.
Weld and lay 20m of 90mm flow line to W4-25 and connect.
Roughly drag flow lines into position.
Install end caps on wells in P4 south.
Service on excavator M379, down for 90 minutes. |
|
26-FEB-2024 |
Richard Andrews |
Drill W4-11 from 20m to 29m. Install pipe and complete well.
Track back across the road. Winch rope came off roller, put back on.
Set up on W3-9, drill and complete to 30.7m.
Set up on W3-15, drill to 5m, seal hole.
Retrench header through road as the angle was difficult to cut tee in for well station connection.
Connect 160mm header to 250mm header. Check falls. |
|
25-FEB-2024 |
Richard Andrews |
Continue drilling W4-10 from 21 to 30.5m. Install well and complete.
Set up on W4-8, drill and complete well to 31m.
Set up on W4-11, drill to 20m. Seal hole.
Weld and lay 150m of 250mm header line.
Trench pipe through rd.
Connect manifolds to 160mm header line and run to 250mm main.
Weld and lay 15m of 160mm header. |
|
24-FEB-2024 |
Richard Andrews |
Track drill rig over to W4-9 and set up.
Drill and complete W4-9 to 31.2m.
Repairs on drill rig.
Set up on W4-10, drill to 21m. Seal hole.
Set up 2 well station manifolds in phase 4. |
|
23-FEB-2024 |
Richard Andrews |
Drill and complete well W3-14 to 31.5m.
Drill and complete well W3-20 to 32m.
Make pad for well station in phase 4.
Down 1 excavator. |