19-FEB-2021 |
|
Drive to Bunnings for latches and signs.
Fit off latches and sign to valve pit near KOP. |
|
06-FEB-2021 |
|
Double check all works.
Check if pumps cycling.
Everything working well. |
|
05-FEB-2021 |
|
Re route condensation line.
Install vent on condensation line. |
|
02-FEB-2021 |
|
Checked if pump worked properly, unbolted head and filled with water.
Met with Geoff from austral checking about shut down.
Resolved condensation issue. |
|
01-FEB-2021 |
|
Set up pump for austral KOP.
Install pump, connect pipe work to valve assembly.
Reconnect pipe work in flare compound. |
|
21-JAN-2021 |
|
Flush out 50mm flow line to clean line for austral.
Currently redirected condensation line into KOP in flare compound.
Erected temp fence to close up flare compound.
(Photos attached) |
|
14-JAN-2021 |
|
Pre start CIP
Ben:
Pick up stickers for pipe labeling, place stickers on pipe.
Mitch, Scott:
Set up leachate pipe in compound. ( once pumps arrived will tie in to existing leachate pipe).
Dug dirt out of way for fence to be reinstated.
Cleaned sand off pipe in compound
Welded leachate side on valve assembly. |
|
13-JAN-2021 |
|
Pre start CIP.
Scott & mitch
Load fittings into Ute and take over to Alan's office, Bunnings to get boxes for fittings.
set up valve assembly.
Mitch
Pick up 2" Valve off josh and 25mm pipe
Ben
Site walk around with Emil.
Reece to pick up fittings for air & leachate in flare compound.
Whipper snipped around the 50mm pipe entering the well from flare compound.
Set up the air connection for Austral KOP.
|
|
12-JAN-2021 |
|
Mitch & Scotty. Sort fittings for valve assembly and pump. Clean container and count fittings.
Ben. Drive from gold coast to Sydney. |
|
25-DEC-2020 |
Russell Clarke |
Travel home for Kieren |
|
24-DEC-2020 |
Russell Clarke |
Backfill around KOP with black road base
Backfill rear tie in point
clean up site of off cuts and rubbish
Demobilise |
|
23-DEC-2020 |
Russell Clarke |
Backfill around 3 coms pits and compact
Backfill and cleanup around flare
Remove loose clay of Cleanaway driveway
Cleanup welding area on top of landfill
Re contour damaged spoon drains
Grade exit road
clean up site of off cuts and rubbish
|
|
22-DEC-2020 |
Russell Clarke |
Drain storm water out of excavations
clean up site of off cuts and rubbish
|
|
21-DEC-2020 |
|
Commissioning of pipeline with Austral
Connection of pipeline both ends |
|
20-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Finish off compacting around KOP and pit.
Weld risers on the leachate and air lines for valve train.
Continued backfilling and compacting. |
|
19-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Backfill and compact around KOP and pit.
Installed Concrete pit around pit ( plastic pit was squishing in due to compaction).
Backfilling and compacting around comms pits and trench line. |
|
18-DEC-2020 |
|
Pre start with CIP, Machine pre starts.
Pressure test on and completed. Passed!
Backfilled and compacted trench.
Loaded out spoil. |
|
17-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Butt weld short on for test point.
Install last of the air and leachate.
All pipe installed, pressure testing tomorrow!
Backfill and compact trench.
|
|
16-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Trench the last of the header line, sand base, install Main header line, Leachate and air.
Load out sand to work area.
Finish off last of the butt welding.
Comms guys onsite.
pulled 490m of optic fiber through comms pipe.
all pipe roped.
|
|
15-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Installed Main header line, air and leachate. 160m total
|
|
14-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Install valve in 1200 pit for KOP
Trench 200m, Installed 120m main header, leachate & air.
|
|
13-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Backfill tidy up road next to the pit & KOP.
Backfill and compact eastern side.
Trench along side the eastern batter.
Butt weld 355 header line.
Sand installed pipe. |
|
12-DEC-2020 |
|
Pre start CIP, Machine pre starts.
Trenched and installed main header, air line & leachate 80m.
Installed KOP and elbowed in the air and leachate.
Butt welding main header. |
|
11-DEC-2020 |
|
Pre start with CIP, Machine pre starts.
Dig out for valve pit and KOP ( KOP yet to be augured)( issue with installing valve in pit as valve was to small!)
Finished backfilling road area near the flare and compacted, tidied up road.
|
|
10-DEC-2020 |
|
Pre start with CIP, machine pre starts.
Installed rest of pipe work to the flare, main header, air, leachate & comms.
Back filled and compacted area through road.
Dug out area for T piece dropper for KOP. ( Storm water running directly under main header was damaged whilst digging out for T piece, need to move over out of way).
|
|
09-DEC-2020 |
|
Pre start with CIP, Machine pre starts.
Installed comms.
Back fill & compact trench behind workshop.
DAILY WORKS
7 Hours hammer and clean out.
Hammer off hired. |
|
08-DEC-2020 |
|
Pre start with CIP, Machine pre starts.
Trenching and installed, main header, air and leachate.
Butt welding main header.
DAILY WORKS
4 hours cutting concrete and breaking out concrete.
5 hours breaking up rock and removing from trench line. |
|
07-DEC-2020 |
|
Pre start with CIP, also toolbox. Pre starts on machines.
Trenching from corner of work shop to back of compound.
Butt welding 355 header line.
DAY WORKS FOR CIP
Kieran pineaha and Ben Gillman.
Quick cutting concrete slab near flare.
8am - 5pm |
|
06-DEC-2020 |
|
Pre start CIP.
Continue on backfilling and compacting and getting the road back accessible.
Ben Ford and Ben Gillman working on variation concrete cutting the slab near the flare.
3hr total plus water cart for variation ( not yet complete). Demo saw supplied by CIP. |
|
05-DEC-2020 |
|
Pre start CIP, Further toolbox to talk about minor incidents from previous day.
Finish trenching from work shop through to flare.
Came across another issue ( concrete slab to far out and doesn't allow us to reach the certain amount of cover required.
Installed pipe work from corner of fence near the work shops to just past the main road crossing.
1.5 HOURS OF FURTHER HAMMERING ONCE CLEANED OUT FROM OTHER EXCAVATOR. |
|
04-DEC-2020 |
|
Pre start with CIP, pre starts on machines.
Finish off compacting and tidying up backfilled area.
Load out sand from top of hill to work area around near flare for weekends works.
Soil test 9am.
Start trenching from workshop back to road.
Hammer for 14.5t machine arrived in the afternoon, hydraulic hose failed, sph mechanic came to fix.
2.5 HOURS OF HAMMERING FOR VARIATION. |
|
03-DEC-2020 |
|
Pre start CIP and machine pre starts.
Installed communication conduit.
Backfilled and compacted all of the area - soil compaction test will be done Friday.
Started trenching from the flare to the road.
Ordered compaction wheel for 14t excavator arrived onsite 1hr later.
Found rock in trench near the flare- will need to obtain rock breaker to get through rock.
|
|
02-DEC-2020 |
|
Pre start with CIP, machine pre starts.
Ben meet truck driver onsite 5:30 for 14t machine to be dropped off.
Vac truck onsite first thing
Exposed around services on road work area.
Mixing soil for compaction and rolling into trench.
Installed gas, air and leachate. 80m
14t not added to the log. |
|
01-DEC-2020 |
|
Pre start with CIP Pre starts on machines.
Continued trenching.
Backfill and compact to reach compaction.
Installed main header, leachate and air. 80m
Soil test taken at 2pm.
8T Machine track fallen off again.
Off hired machine due to track issues.
|
|
30-NOV-2020 |
|
Pre start on machines and pre start with CIP
Installed comms pipe.
Backfilled and compacted some of the trench.
Continue trenching.
Sanded trench for next length to be installed.
2 x machine break downs today resulting in a bit of downtime.
14t hydraulic hose in the back blew out, matt SPH had someone come out to fix it.
8t both tracks came off machine, didn't bother contacting matt again just fixed the issue ourselves. |
|
29-NOV-2020 |
|
Sand up trench and compact.
Install pipe work sand over and compact that also.
Gps top of pipe and bottom of trench |
|
28-NOV-2020 |
|
Finish off bulking out along side fence.
Silt fence along fence.
Tidy up dirt stock piles.
Trench from tie in point back, roughly 90m.
Cart sand to work area.
Butt welding main header line |
|
27-NOV-2020 |
|
Butt weld 355 header
Start on bulking out along side the fence near tie in spot for trench line.
Trench near tie in point.
|
|
26-NOV-2020 |
|
Pre starts on all machines, pre start with CIP'.
Installed comms line.
Backfilled and compacted trench.
Cleaned off grass and top soil from next trench area.
Butt welded 355 pipe
Richard
Variation for CIP
2.5 hours today
Spreading out gravel for offices and containers |
|
25-NOV-2020 |
|
Site Pre start & machines pre starts.
Continue trenching, installed header, leachate & air. 80m total.
Load out rocks from spoil dug out of trench.
Gps bottom of trench and top of pipe.
Load sand to work area from stockpile.
Compact one layer of dirt.
Machines arrived and removed from site.
Manitou picked up 8am 20t picked up 10am. dump truck, 8t and trench compactor arrived onsite. |
|
24-NOV-2020 |
|
Butt welding 355 header.
Uncoil 110 pipe.
Vac truck to identify services.
Remove and level out bund wall for trench line.
Started trenching.
(20T excavator will be swapped out due to not being suitable for task). Last day billed 24th. |
|
23-NOV-2020 |
|
Collect and unload deliveries.
Site walk with Reg Blair. |
|
22-NOV-2020 |
|
No works |
|
21-NOV-2020 |
|
Remove grass from excavation area.
GPS site again due to error first time.
|
|
20-NOV-2020 |
|
Waited for deliveries: Container, excavator, tnt delivery
Picked up all tagged gear from Run office.
Ben (telehandler ticket).
Arrived back on site 1pm. went over issues with CIP and Paul from Cleanaway. Site walk on services.
All equipment in notes on the input as not in system. |
|
19-NOV-2020 |
|
Pre start meeting with nick from CIP
Bunnings to pick up pegs.
GPS new header line |