27-JUN-2020 |
|
Clean SPH machines and store ready to be picked up.
Clean lunchroom and containers.
General site tidy up |
|
26-JUN-2020 |
|
Load container for transportation to WA.
Finish off doing pads around Bara Trap risers 2.5hrs.
Cart dirt for G67 pad to be made 2meters. 2.5hrs
Install flex hose to wellsG67,68.
General tidy up of site.
Off hire SPH 14T , 6T Excavators & Moxy. |
|
25-JUN-2020 |
|
Installed well heads on F31,A42,G67
Dayne building pads for finished wells G16,17,25,69,68, total hrs to complete pads 7.5hrs
David building pads for finished wells A44,43,42,33, G34,35, total hrs to complete pads 2.5hrs
Trench in flow line for G67 10mx 90mm install well head, back fill and clean up trench.
SPH picked up telehandler |
|
24-JUN-2020 |
|
Get Richard's tool container packed ready to be transported to WA being picked up Friday morning.
Tie in flow line to A42 well and install riser at 160mm header line, backfill and tidy trench line, restate V drain next to A42 stringer.
Trench in flow line to well F31 45m x 90mm pipe and tie into 160mm Lateral header line running down batter towards flare, backfill and tidy trench line.
Mark gone to west connect. |
|
23-JUN-2020 |
|
Sand up trench and installed 50mts x 90mm flow line and backfill, left lateral header line and stringer ends open for tie in.
Mark/ Dayne heading to West Connect |
|
22-JUN-2020 |
|
Finish off backfilling trench for well A44, Installed 225mm hard cap to stringer, Installed A44 standalone well head 160mm onto 160mm lateral header line & Flexi hose.
Installed G35 standalone well head 225mm & Flexi hose.
Installed G17 standalone well head 225mm, 1.5m of 225mm pipe added to well head.
Installed G25 standalone well head 225mm, 1.7m of 225mm pipe added to well head.
Installed G69 standalone well head 225mm, 1.2m of 225mm pipe added to well head.
All Wells require dirt for pads to get them up to finished levels
Trench 50m for Well A42, cut in 160mm tee to lateral header line for 160 standalone well head. |
|
21-JUN-2020 |
|
Day off |
|
20-JUN-2020 |
|
Finish off building pads at wells G68, 15.
Trench down from 160mm lateral header line to well A43 for flow line tie into stringer, 40mts. Install 225mm saddle and tie flow line in.
SPH 6T excavator throw a track off on machine rang Lee from SPH he organised a plant mechanic to come to site to put track back on 5hrs downtime on machine.
Installed well heads and Flexi hose on wells G34,35 & A43 completed.
Finish off trenching alone toe of hall road batter to run flow line in on well A44, had to add 6mts of 90mm pipe that was already installed hanging out of trench Installed 225mm saddle and hook flow line up. |
|
19-JUN-2020 |
|
Finished off back filling trench E09, install standalone well head and flex hose ,cart rubbish to tip face.
Trench in flow lines for wells G69, G15.
G15 install flex hose to flow line completed.
Completed well G68 installed 225mm saddle and hooked in flow line, back fill/ tidy area, cart rubbish to tip face.
Exposed 160mm header line for wells A42,43 for tee’s to be cut into header line.
Cart dirt for pads at wells G68, G19, time taken = 1hr
|
|
18-JUN-2020 |
|
Install well heads on wells to finished heights G068, G016, G015, E09, all well heads have had extra pipe butt welded on them to get heads up at correct finished heights, G68 = 1.8Mts of 160mm, G19 = 1.5Mts of 160mm, G16 = 2.0Mts of 225mm, E09, G15 were at finished heights didn't require any extra pipe.
Trenched in flow line for well E09 = 52m x 90mm.
Raised Bara Trap filler tubes on 5 Traps by another 3mts. |
|
17-JUN-2020 |
|
trench header extension to above well G068.
SPH delivery of Auger to drill hole for Bara Trap and install trap near well G068.
Cut in 160 tee into header line for well G068 well head, run flow line down to 225 riser cannot hook up as we don't have any 225mm saddles.
Run flow line for Well G019 and build pad to finished height and install well head.
Kieran making pads around drilled wells for finished heights, Wells G017,016,025,19 time was 4hrs to complete. |
|
16-JUN-2020 |
|
Well A42 finished off bentonite seal and clay cap.
well head preps install nipples etc.
45m 160mm header line installed for header extension.
Started digging in Bara Trap cannot get reach with the digger require 600mm auger from SPH.
Cart rock and sand for trench and bara trap.
Demob drill rig give Shane a hand to clean and pack tooling up ready for transport to Tamworth. |
|
15-JUN-2020 |
|
Carry on Drilling last two wells A42, F031, still drilling with auger as we are waiting on drill spike to be repaired.
Buttweld 1.5m of 160mm pipe to 4 standalone well heads for connection to 160mm header line.
Butt weld 160mm pipe for header line extension.
Expose 90mm flow line to well G068 and relay in trench for new well head location off 160mm header line.
Wells F031, A42 completed drilling finished. |
|
14-JUN-2020 |
|
day off |
|
13-JUN-2020 |
|
replaced faulty saddle on flow line to header back filled and cleaned up area (lee)
complete well A44 and well A43 ( dayne, ben)
|
|
12-JUN-2020 |
|
Well G15 completed
Well A44 drilled to 28m ( drilling with auger much slower ) (ben g,hayden )
trench and back fill G25 flow line
back fill flow line G68 (Lee, Luke )
gps migration wells
gps all installed items on site
fix header line hit by dozer and clean up area
fix header hit by excavator |
|
11-JUN-2020 |
|
barra trap welded and completed
well E09 drilled and completed
well G15 drilled to 24.7m (drill crew luke and ben greenwood) (spike snapped for drill rig again resolving issue in the morning).
flow lines for wells G34 and A33
ben f ( bunnings to pick up materials, pick up chains from elizabeth dr container, pick up delivery for at kemps creek for civil group.
trench flow line for well G68
finished off trenching lateral header line |
|
10-JUN-2020 |
|
meet mechanic for generator/fuel cell (ben ford ) 6am
install 2 barra traps, 3rd barra trap drilled and in trench but not completed.
clean up rubbish on top area and stockpile dirt for future use.
help set up new drill rig
trench in flow lines.( will finish once 90mm elbows arrive).
|
|
09-JUN-2020 |
|
trench lateral header line and install (Ben, lee)
completed well A33
dig out and install flow lines for wells
G16, G17 , G35 (Luke, Ben)
pack up drill rig (hayden)
|
|
08-JUN-2020 |
|
trench 20m off lateral header line
well G35 complete
well A33 drilled 35m (Luke, Hayden)
did road crossing across haul road for flow line to well A44
tidy up and compact road. (Ben, lee)
prep up barra traps ready for install. (Ben.g)
tidy up and stockpile rubbish from over weekend
|
|
07-JUN-2020 |
|
day off |
|
06-JUN-2020 |
|
well G16 completed
well G34 completed
(Luke,Hayden) drill crew
lateral header trenched and installed back filled and cleaned up
(Ben, lee) |
|
05-JUN-2020 |
|
kicker and luke sort out drill logs
lee and hayden set up laser and mark out lateral header line
luke pick up spike for civil group
(luke,kicker,hayden) drill crew
lee and ben trenching
(in installation items well metres drilled the 12.5 is left over depth from well G25)
well G25 completed |
|
04-JUN-2020 |
|
drilling (drill crew, kicker and luke and when available hayden.
tie in header down bottom of batter, installed vavle pit, 8". ( Ben,lee, Hayden).
well g17 installed.
well g25 (27.5m)
cleanded out valve pit and sealed pit.
gps current pipe installed.
|
|
03-JUN-2020 |
|
clean up header area at bottom of batter.
set up vavle pit and pit base
trench and install 160mm header line
install barra trap
drill rig drilled 25m with orgre |
|
02-JUN-2020 |
|
lay and backfill 160mm header line
trench and lay 200mm header line and prep for tie in
set up pads for drill rig |
|
01-JUN-2020 |
|
continue trenching 160mm header line
continue trenching 200mm header line
butt weld reducer 315-225-200
drill rig arrived 12pm. remob from elizabeth |
|
31-MAY-2020 |
|
day off |
|
30-MAY-2020 |
|
finish welding 160mm header line
continue trenching 200mm header line down batter
set out stringers near locations
lay and back fill header |
|
29-MAY-2020 |
|
expose 31mm5 header line along side road
continue butt welding 160mm header line
trench 200mm header line down batter |
|
28-MAY-2020 |
|
continue on with butt welding 225 stringers
excavate 160 header line, lay and backfill 85m |
|
27-MAY-2020 |
|
butt welding 160 header and 225 stringers
trench 160 header line |
|
26-MAY-2020 |
|
continue butt welding 225 stringers, 200 header line ( butt weld logs added in)
gps well re drill |
|
25-MAY-2020 |
|
Start butt welding 160mm pipe.
Hire container delivered to site, put fittings in container.
Telehandler delivered to site.
Generator requires oil keeps going off on low oil level. |
|
22-MAY-2020 |
|
LC travel home. |
|
21-MAY-2020 |
|
Butt welding.
Heavy rain from 9am.
Clean up containers.
Rained off 11am. |
|
20-MAY-2020 |
|
Drop GPS off at Elizabeth drive.
Drop Ben at astina to pack his bags and then pick up hire car.
Ben Ford drive back to Gold Coast.
Pick up Lee from course.
Sort out pipe and prep butt welders ready for tomorrow. |
|
19-MAY-2020 |
|
take off on fittings and pipe on site
set up lunchroom/office |